09.12.2022 Views

Operations and Supply Chain Management The Core

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

MATERIAL REQUIREMENTS PLANNING chapter 9 279

An MRP record is kept for each item managed by the system. The record contains

gross requirements, scheduled receipts, projected available balance, net requirements,

planned-order receipts, and planned-order releases data. Gross requirements are the total

amount required for a particular item. These requirements can be from external customer

demand and also from demand calculated due to manufacturing requirements. Scheduled

receipts represent orders that have already been released and that are scheduled to arrive

as of the beginning of the period. Once the paperwork on an order has been released, what

was prior to that event’s “planned” order now becomes a scheduled receipt. Projected

available balance is the amount of inventory expected as of the end of a period. This can

be calculated as follows:

Projected Projected

available = available − Gross + Scheduled Planned-

+ order

requirements

balance t balance t receipts t

t–1 receipts t

One thing that needs to be considered is the initial projected available balance. In the

case where safety stock is needed, the on-hand balance needs to be reduced by the safety

stock. So, projected available balance in period zero is on-hand minus the safety stock.

A net requirement is the amount needed when the projected available balance plus the

scheduled receipts in a period are not sufficient to cover the gross requirement. The plannedorder

receipt is the amount of an order that is required to meet a net requirement in the

period. Finally, the planned-order release is the planned-order receipt offset by the lead time.

Beginning with meter A, the projected available balance is 50 units and there are no

net requirements until week 9. In week 9, an additional 1,200 units are needed to cover

the demand of 1,250 generated from the order scheduled through the master schedule. The

order quantity is designated “lot-for-lot,” which means that we can order the exact quantity

needed to meet net requirements. An order, therefore, is planned for receipt of 1,200 units

for the beginning of week 9. Since the lead time is two weeks, this order must be released

at the beginning of week 7.

Meter B is similar to A, although an order for 10 units is scheduled for receipt in

period 5. We project that 70 units will be available at the end of week 5. There is a net

requirement for 400 additional units to meet the gross requirement of 470 units in week 9.

This requirement is met with an order for 400 units that must be released at the beginning

of week 7.

Item C is the subassembly used in both meters A and B. We need additional Cs only

when either A or B is being made. Our analysis of A indicates that an order for 1,200 will

be released in week 7. An order for 400 Bs also will be released in week 7, so the total

demand for C is 1,600 units in week 7. The projected available balance is the 40 units

on-hand minus the safety stock of 5 units we have specified, or 35 units. In week 7, the

net requirement is 1,565 units. The order policy for C indicates an order quantity of 2,000

units, so an order receipt for 2,000 is planned for week 7. This order needs to be released

in week 6 due to the one-week lead time. Assuming this order is actually processed in the

future, the projected available balance is 435 units in weeks 7, 8, and 9.

Item D, the transformer, has demand from three different sources. The demand in week

6 is due to the requirement to put Ds into subassembly C. In this case, two Ds are needed

for every C, or 4,000 units (the product structure indicates this two-to-one relationship).

In the seventh week, 1,200 Ds are needed for the order for 1,200 As that are scheduled to

be released in week 7. Another 270 units are needed in week 9 to meet the independent

demand that is scheduled through the master schedule. The projected available balance at

the end of week 4 is 280 units (200 on-hand plus the scheduled receipt of 100 units minus

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!