09.12.2022 Views

Operations and Supply Chain Management The Core

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

PROJECTS chapter 5 141

1 3

0 1

A(1)

0 1

B(2)

1 3

1 2

C(1)

3 4

D(1)

3 4

2 3

Example 5.2: Critical Path Method

Many firms that have tried to enter the notebook computer market have failed. Suppose your firm

believes there is a big demand in this market because existing products have not been designed correctly.

They are too heavy, too large, or too small to have standard-sized keyboards. Your intended

computer will be small enough to carry inside a jacket pocket if need be. The ideal size will be no

larger than 5 inches × 9½ inches × 1 inch with a folding keyboard. It should weigh no more than 15

ounces and have an LCD display, a solid state drive, and a wireless bluetooth connection. This should

appeal to traveling businesspeople, but it could have a much wider market, including students. It

should be priced in the $175–$200 range.

The project, then, is to design, develop, and produce a prototype of this small computer. In the

rapidly changing computer industry, it is crucial to hit the market with a product of this sort in less

than a year. Therefore, the project team has been allowed approximately eight months (35 weeks) to

produce the prototype.

Excel: Project

Management

SOLUTION

The first charge of the project team is to develop a project network chart and determine if the prototype

computer can be completed within the 35-week target. Let’s follow the steps in the development

of the network.

1. Activity identification. The project team decides that the following activities are the major

components of the project: design of the computer, prototype construction, prototype testing,

methods specification (summarized in a report), evaluation studies of automatic assembly

equipment, an assembly equipment study report, and a final report summarizing all aspects of

the design, equipment, and methods.

2. Activity sequencing and network construction. On the basis of discussion with staff, the

project manager develops the precedence table and sequence network shown in Exhibit 5.6.

When constructing a network, take care to ensure that the activities are in the proper order and

that the logic of their relationships is maintained. For example, it would be illogical to have a

situation where event A precedes event B, B precedes C, and C precedes A.

3. Critical path determination. The critical path is the longest sequence of connected activities

through the network and is defined as the path with zero slack time. This network has four

different paths: A–C–F–G, A–C–E–G, A–B–D–F–G, and A–B–D–E–G. The lengths of these

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!