09.12.2022 Views

Operations and Supply Chain Management The Core

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

PROJECTS chapter 5 135

Earned Value Management Charts

exhibit 5.5

Chart A

Chart B

Budgeted Cost of Work Scheduled (BCWS)

Actual Cost (AC)

Budgeted Cost of Work Scheduled (BCWS)

Budgeted Cost of Work Performed (BCWP)

$200,000

$200,000

BCWS

$150,000

$100,000

$50,000

BCWS

AC

Project

Tracking

without

Earned Value

Is Inconclusive

$150,000

$100,000

$50,000

BCWP

Behind

Schedule

Schedule

Variance (Time)

Schedule

Variance ($)

$0

1 2 3 4 5 6 7 8

Time (weeks)

9

10 11 12

$0

1 2 3 4 5 6 7 8

Time (weeks)

9

10 11 12

Chart C

Chart D

$200,000

Budgeted Cost of Work Performed (BCWP)

Actual Cost (AC)

$200,000

Budgeted Cost of Work Scheduled (BCWS)

Budgeted Cost of Work Performed (BCWP)

Actual Cost (AC)

BCWS

$150,000

$150,000

$100,000

$50,000

BCWP

AC

Cost

Variance ($)

Underbudget

$100,000

$50,000

BCWP

AC

$0

1 2 3 4 5 6 7 8

Time (weeks)

9

10 11 12

$0

1 2 3 4 5 6 7 8

Time (weeks)

9 10 11 12

planned in detail, including a time-phased spend plan for all elements of work. This is

a case where the project is evaluated based on cost. Exhibit 5.5A shows the cumulative

cost budget for this project as a function of time (the blue line, labeled BCWS). It also

shows the cumulative actual cost of the project (red line) through week 8. To those unfamiliar

with EVM, it might appear that this project was overbudget through week 4 and

then underbudget from week 6 through week 8. However, what is missing from this chart

is any understanding of how much work has been accomplished during the project. If the

project was actually completed at week 8, then the project would be well underbudget and

far ahead of schedule. If, on the other hand, the project is only 10 percent complete at week

8, then the project is significantly overbudget and behind schedule. A method is needed

to measure technical performance objectively and quantitatively, and that is what EVM

accomplishes.

Project Tracking with EVM Consider the same project, except this time the project plan

includes predefined methods of quantifying the accomplishment of work. At the end of each

week, the project manager identifies every detailed element of work that has been completed,

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!