09.12.2022 Views

Operations and Supply Chain Management The Core

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

142 OPERATIONS AND SUPPLY CHAIN MANAGEMENT

exhibit 5.6

CPM Network for Computer Design Project

CPM Activity Designations and Time Estimates

Activity

Designation

Immediate

Predecessors

Time

(weeks)

Design

Build prototype

Evaluate equipment

Test prototype

Write equipment report

Write methods report

Write final report

A

B

C

D

E

F

G

A

A

B

C, D

C, D

E, F

21

5

7

2

5

8

2

C(7)

F(8)

A(21)

G(2)

B(5) D(2) E(5)

paths are 38, 35, 38, and 35 weeks. Note that this project has two different critical paths; this

might indicate that this would be a fairly difficult project to manage. Calculating the early

start and late start schedules gives additional insight into how difficult this project might be

to complete on time.

Early start schedule

A project schedule

that lists all activities

by their early start

times.

Late start schedule

A project schedule

that lists all activities

by their late start

times. This schedule

may create savings

by postponing

purchases of

material and other

costs associated with

the project.

Early Start and Late Start Schedules An early start schedule is one that lists all of the

activities by their early start times. For activities not on the critical path, there is slack time

between the completion of each activity and the start of the next activity. The early start

schedule completes the project and all its activities as soon as possible.

A late start schedule lists the activities to start as late as possible without delaying the

completion date of the project. One motivation for using a late start schedule is that savings

are realized by postponing purchases of materials, the use of labor, and other costs

until necessary. These calculations are shown in Exhibit 5.7. From this, we see that the

only activity that has slack is activity E. This certainly would be a fairly difficult project to

complete on time.

CPM with Three Activity Time Estimates

If a single estimate of the time required to complete an activity is not reliable, the best

procedure is to use three time estimates. These three times not only allow us to estimate

the activity time but also let us obtain a probability estimate for completion time for the

entire network. Briefly, the procedure is as follows: The estimated activity time is calculated

using a weighted average of a minimum, maximum, and most likely time estimate.

The expected completion time of the network is computed using the procedure described

above. Using estimates of variability for the activities on the critical path, the probability

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!