09.12.2022 Views

Operations and Supply Chain Management The Core

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

146 OPERATIONS AND SUPPLY CHAIN MANAGEMENT

Probability Analysis

The three-time-estimate approach introduces the ability

to consider the probability that a project will be completed

within a particular amount of time. The assumption needed

to make this probability estimate is that the activity duration

times are independent random variables. If this is true, the

central limit theorem can be used to find the mean and the

variance of the sequence of activities that form the critical

path. The central limit theorem says that the sum of a group

of independent, identically distributed random variables

approaches a normal distribution as the number of random

variables increases. In the case of project management

problems, the random variables are the actual times for the

activities in the project. (Recall that the time for each activity

is assumed to be independent of other activities

and to follow a beta statistical distribution.) For

this, the expected time to complete the critical

path activities is the sum of the activity times.

Likewise, because of the assumption of

activity time independence, the sum of the variances

of the activities along the critical path is

the variance of the expected time to complete

the path. Recall that the standard deviation is

equal to the square root of the variance.

To determine the actual probability of completing

the critical path activities within a certain

amount of time, we need to find where on our

probability distribution the time falls. Appendix E

shows the areas of the cumulative standard normal distribution

for different values of Z. Z measures the number of

standard deviations either to the right or to the left of zero

in the distribution. The values correspond to the cumulative

probability associated with each value of Z. For example,

the first value in the table, −4.00, has a G(z) equal to

0.00003. This means that the probability associated with a

Z value of −4.0 is only 0.003 percent. Similarly, a Z value of

1.50 has a G(z) equal to 0.93319 or 93.319 percent. The

Z values are calculated using equation 5.3, given in step

7b of the “Three Time Estimates” example solution. These

cumulative probabilities also can be obtained by using the

NORM.S.DIST(Z,TRUE) function built into Microsoft Excel.

Negative values of Z

Probability

of Z

0

Positive values of Z

Minimum-Cost Scheduling (Time–Cost Trade-Off) The basic assumption in minimumcost

scheduling, also known as “crashing,” is that there is a relationship between activity

completion time and the cost of a project. Crashing refers to the compression or shortening

of the time to complete the project. It costs money to expedite an activity, and these costs

are termed activity direct costs and add to the project direct cost. Some may be workerrelated,

such as scheduling overtime work, hiring more workers, and transferring workers

from other jobs; others are resource-related, such as buying or leasing additional or more

efficient equipment and drawing on additional support facilities.

The costs associated with sustaining the project are termed project indirect costs: overhead,

facilities, and resource opportunity costs, and, under certain contractual situations,

penalty costs or lost incentive payments. Because activity direct costs and project indirect

costs are opposing costs dependent on time, the scheduling problem is essentially one of

finding the project duration that minimizes their sum, or in other words, finding the optimum

point in a time–cost trade-off.

The procedure for project crashing consists of the following five steps. It is explained

by using the simple four-activity network shown in Exhibit 5.10. Assume that the indirect

costs remain constant at $10 per day if the project takes eight days or less and then

increases at the rate of $5 per day.

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!