09.12.2022 Views

Operations and Supply Chain Management The Core

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

PROJECTS chapter 5 139

group will consider. During this meeting, you will split your group in half: Two people will

be responsible for the annual report and ratio analysis, and the other two will collect the

technical data and construct the charts. Your group expects it to take two weeks to get the

annual report and perform the ratio analysis, and a week to collect the stock price data and

generate the charts. You agree that the two groups can work independently. Finally, you

agree to meet as a team to make the purchase decision. Before you meet, you want to allow

one week for each team member to review all the data.

This is a simple project, but it will serve to demonstrate the approach. The following are

the appropriate steps:

1. Identify each activity to be done in the project and estimate how long it will

take to complete each activity. This is simple, given the information from your

instructor. We identify the activities as follows: A(1), B(2), C(1), D(1). The number

is the expected duration of the activity.

2. Determine the required sequence of activities and construct a network

reflecting the precedence relationships. An easy way to do this is to first identify

the immediate predecessors associated with an activity. The immediate

predecessors are the activities that need to be completed immediately before an

activity. Activity A needs to be completed before activities B and C can start. B

and C need to be completed before D can start. The following table reflects what

we know so far:

ACTIVITY

DESIGNATION

IMMEDIATE

PREDECESSORS

TIME

(WEEKS)

Select company A None 1

Obtain annual report and perform ratio analysis B A 2

Collect stock price data and perform technical analysis C A 1

Review data and make a decision D B and C 1

Here is a diagram that depicts these precedence relationships:

Immediate

predecessors

Activities that need

to be completed

immediately before

another activity.

Report and Ratio Analysis

Select

Company

B(2)

Make

Decision

A(1)

D(1)

C(1)

Technical Analysis

3. Determine the critical path. Consider each sequence of activities that runs from

the beginning to the end of the project. For our simple project there are two paths:

A–B–D and A–C–D. The critical path is the path where the sum of the activity

times is the longest. A–B–D has a duration of four weeks and A–C–D has a duration

of three weeks. The critical path, therefore, is A–B–D. If any activity along the

critical path is delayed, then the entire project will be delayed.

4. Determine the early start/finish and late start/finish schedule. To schedule

the project, find when each activity needs to start and when it needs to finish.

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!