140 OPERATIONS AND SUPPLY CHAIN MANAGEMENT

Slack time

The time that an

activity can be

delayed without

delaying the

entire project; the

difference between

the late and early

start times of an

activity.

For some activities in a project, there may be some leeway regarding when an activity

can start and finish. This is called the slack time in an activity. For each activity

in the project, we calculate four points in time: the early start, early finish, late

start, and late finish times. The early start and early finish are the earliest times that

the activity can start and be finished. Similarly,

the late start and late finish are the latest times

the activities can start and finish without delaying

the project. The difference between the late

start time and early start time is the slack time.

To help keep all of this straight, we place these

numbers in special places around the nodes that

represent each activity in our network diagram,

as shown here.

Early

start

Late

start

Activity

(duration)

Early

finish

Late

finish

To calculate numbers, start from the beginning of the network and work to the

end, calculating the early start and early finish numbers. Start counting with the

current period, designated as period 0. Activity A has an early start of 0 and an

early finish of 1. Activity B’s early start is A’s early finish or 1. Similarly, C’s early

start is 1. The early finish for B is 3, and the early finish for C is 2. Now consider

activity D. D cannot start until both B and C are done. Because B cannot be done

until 3, D cannot start until that time. The early start for D, therefore, is 3, and the

early finish is 4. Our diagram now looks like this.

1 3

0 1

B(2)

3 4

A(1)

1 2

D(1)

C(1)

To calculate the late finish and late start times, start from the end of the network

and work toward the front. Consider activity D. The earliest that it can be done is

at time 4; and if we do not want to delay the completion of the project, the late finish

needs to be set to 4. With a duration of 1, the latest that D can start is 3. Now

consider activity C. C must be done by time 3 so that D can start, so C’s late finish

time is 3 and its late start time is 2. Notice the difference between the early and late

start and finish times: This activity has one week of slack time. Activity B must be

done by time 3 so that D can start, so its late finish time is 3 and late start time is 1.

There is no slack in B. Finally, activity A must be done so that B and C can start.

Because B must start earlier than C, and A must get done in time for B to start, the

late finish time for A is 1. Finally, the late start time for A is 0. Notice there is no

slack in activities A, B, and D. The final network looks like this. (Hopefully, the

stock your investment team has chosen is a winner!)