09.12.2022 Views

Operations and Supply Chain Management The Core

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

PROJECTS chapter 5 147

Example of Time–Cost Trade-Off Procedure

exhibit 5.10

Step 1. Prepare CPM Diagram with Activity Costs

Step 2. Determine Cost per Unit of Time

CT

NT

NC

CC

2, 1

A

$6, $10

CC Crash cost

CT Crash time

NC Normal cost

NT Normal time

5, 2

B

$9, $18

4, 3

C

$6, $8

0

0

3, 1

D

$5, $9

Activity

cost

$10

8

6

CC, CT

NC, NT

Activity A

1 2 3 4

Time

Step 3. Compute the Critical Path

2 7

B(5)

A(2)

2

2

2

2

3

C(4)

7

6

7

7

7

D(3)

10

10

Excel: Project

Management

1. Prepare a CPM-type network diagram. For each activity, this diagram should list:

a. Normal cost (NC): the lowest expected activity costs. (These are the lesser of

the cost figures shown under each node in Exhibit 5.10.)

b. Normal time (NT): the time associated with each normal cost.

c. Crash time (CT): the shortest possible activity time.

d. Crash cost (CC): the cost associated with each crash time.

2. Determine the cost per unit of time (assume days) to expedite each activity. The

relationship between activity time and cost may be shown graphically by plotting

CC and CT coordinates and connecting them to the NC and NT coordinates by a

concave, convex, or straight line—or some other form, depending on the actual cost

structure of activity performance, as in Exhibit 5.10. For activity A, we assume a

linear relationship between time and cost. This assumption is common in practice

and helps us derive the cost per day to expedite because this value may be found

directly by taking the slope of the line using the formula Slope = (CC − NC) ÷

(NT − CT). (When the assumption of linearity cannot be made, the cost of expediting

must be determined graphically for each day the activity may be shortened.)

The calculations needed to obtain the cost of expediting the remaining activities

are shown in Exhibit 5.11A.

3. Compute the critical path. For the simple network we have been using, this

schedule would take 10 days. The critical path is A–B–D.

4. Shorten the critical path at the least cost. The easiest way to proceed is to start

with the normal schedule, find the critical path, and reduce the path time by one

day using the lowest-cost activity. Then recompute and find the new critical path

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!