PROJECTS chapter 5 133

Sample of Graphic Project Reports

exhibit 5.4

A. Gantt Chart for Single Activities

Activity

Contract

negotiated

Contract

signed

Long lead

procurement

Manufacturing

schedules

Bill-ofmaterials

Short lead

procurement

Material

specifications

Manufacturing

plans

Start-up

Dollars $

B. Total Program Cost Breakdown

Total $

Overhead $

Material $

Labor $

Time

2

4 6 8 10 12 14 16

Weeks after start of project

18

20

D. Cost and Performance Tracking Schedule

Project 1

C. Divisional Breakdown of Costs and Labor Hours

Percentage of labor hours

Percentage of cost

50

Manufacturing

40

Project 2

Project 3

Projected

Completed

20

15

10

Finance

Engineering

Overhead

10

15

25

Total

program

costs $

Time

Projected

Actual

Overruns

5

Personnel

10

60 40 20 0

0 20 40

Time

Tracking date line

E. Bar/Milestone Chart

Short lead

procurement

1 2 3

9 10 11

Weeks after start of project

Milestones

1. Purchase order release

2. Invoices received

3. Material received