09.12.2022 Views

Operations and Supply Chain Management The Core

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

MATERIAL REQUIREMENTS PLANNING chapter 9 275

2. Next, the program uses the current on-hand balance together with the schedule of

orders that will be received in the future to calculate the “net requirements.” Net

requirements are the amounts that are needed week by week in the future over and

above what is currently on-hand or committed to through an order already released

and scheduled.

3. Using net requirements, the program calculates when orders should be received to

meet these requirements. This can be a simple process of just scheduling orders to

arrive according to the exact net requirements or a more complicated process where

requirements are combined for multiple periods. This schedule of when orders

should arrive is referred to as “planned-order receipts.”

4. Since there is typically a lead time associated with each order, the next step is to

find a schedule for when orders are actually released. Offsetting the planned-order

receipts by the required lead time does this. This schedule is referred to as the

“planned-order release.”

5. After these four steps have been completed for all the level zero items, the program

moves to level 1 items.

6. The gross requirements for each level 1 item are calculated from the planned-order

release schedule for the parents of each level 1 item. Any additional independent

demand also needs to be included in the gross requirements.

7. After the gross requirements have been determined, net requirements, planned-order

receipts, and planned-order releases are calculated as described in steps 2–4 above.

8. This process is then repeated for each level in the bill-of-materials.

The process of doing these calculations is much simpler than the description, as you

will see in the example that follows. Typically, the explosion calculations are performed

each week or whenever changes have been made to the master schedule. Some MRP

programs have the option of generating immediate schedules, called net change schedules.

Net change systems are “activity” driven and requirements and schedules are

updated whenever a transaction is processed that has an impact on the item. Net change

enables the system to reflect in “real time” the exact status of each item managed by

the system.

Net change systems

An MRP system

that calculates

the impact of a

change in the MRP

data (the inventory

status, BOM, or

master schedule)

immediately.

AN EXAMPLE USING MRP

Ampere, Inc. produces a line of electric meters installed in residential buildings by

electric utility companies to measure power consumption. Meters used on single-family

homes are of two basic types for different voltage and amperage ranges. In addition to

complete meters, some subassemblies are sold separately for repair or for changeovers

to a different voltage or power load. The problem for the MRP system is to determine a

production schedule to identify each item, the period it is needed, and the appropriate

quantities. The schedule is then checked for feasibility, and the schedule is modified

if necessary.

LO9–3 Analyze an

MRP problem.

Forecasting Demand

Demand for the meters and components originates from two sources: regular customers

that place firm orders in advance based on the needs of their projects; and other, typically

smaller, customers that buy these items as needed. The smaller customer requirements

were forecast using one of the usual techniques described in Chapter 3 and past demand

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!