09.12.2022 Views

Operations and Supply Chain Management The Core

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

MATERIAL REQUIREMENTS PLANNING chapter 9 289

Notes:

1. For item A, start by calculating the projected available balance through week 2. In week 3,

there is a net requirement for 17 units, so we plan to receive an order for 20 units. Projected

available balance for week 3 is three units and a net requirement for five in week 4, so we

plan another order to be received in week 4. Projected available balance for week 4 is 15

units, with three in week 5 and a net requirement for 19 in week 6. We need to plan one more

order for receipt in week 6.

2. The gross requirements for B are based on two times the planned order releases for A. We

need to account for the scheduled receipt in week 1 of 32 units, resulting in a projected available

balance of 52 at the end of week 1.

3. The gross requirements for C are based on the planned order releases for items A and B, since

C is used in both items. The projected available balance is calculated by subtracting out the

safety stock since this inventory is kept in reserve. In week 1, for example, projected available

balance is 70 units on-hand − 40 units gross requirements − 10 units safety stock = 20 units.

LO9–4 SOLVED PROBLEM 4

Consider the following data relevant to an MRP lot-sizing problem:

Item cost per unit $25

Setup cost $100

Inventory carrying cost per year 20.8%

WEEKLY NET REQUIREMENTS

1 2 3 4 5 6 7 8

105 80 130 50 0 200 125 100

Use the four lot-sizing rules in the chapter to propose an MRP schedule under each rule. Assume

there is no beginning inventory.

Solution

Lot-for-Lot

The lot-for-lot rule is very commonly used because it is so simple and intuitive. The planned-order

quantities are equal to the net requirements each week.

WEEK

REQUIREMENTS

NET

PRODUCTION

QUANTITY

ENDING

INVENTORY

HOLDING

COST

SETUP

COST

TOTAL

COST

1 105 105 0 $0.00 $100.00 $100.00

2 80 80 0 0.00 100.00 200.00

3 130 130 0 0.00 100.00 300.00

4 50 50 0 0.00 100.00 400.00

5 0 0 0 0.00 100.00 500.00

6 200 200 0 0.00 100.00 600.00

7 125 125 0 0.00 100.00 700.00

8 100 100 0 0.00 100.00 800.00

Economic Order Quantity

We need D, S, and H in the EOQ formula. We will estimate annual demand based on average

weekly demand over these 8 weeks.

D = Annual demand = _______________________________

105 + 80 + 130 + 50 + 0 + 200 + 125 + 100

​ ​ × 52 = 5,135

8

H = Annual holding cost = 0.208 × $25.00 = $5.20

S = Setup cost = $100 (given) ​

____

EOQ = ​ √

​ ____ 2DS

____________

H ​ = ​ √

​ ___________

2(5135)(100) ​ = 444

5.20

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!