09.12.2022 Views

Operations and Supply Chain Management The Core

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

276 OPERATIONS AND SUPPLY CHAIN MANAGEMENT

exhibit 9.9

Future Requirements for Meters A and B and Subassembly D

Stemming from Specific Customer Orders and from Forecasts

METER A METER B SUBASSEMBLY D

MONTH KNOWN FORECAST KNOWN FORECAST KNOWN FORECAST

3 1,000 250 410 60 200 70

4 600 250 300 60 180 70

5 300 250 500 60 250 70

exhibit 9.10

A Master Schedule to Satisfy Demand Requirements as

Specified in Exhibit 9.9

Week

9 10 11 12 13 14 15 16 17

Meter A

1,250

850

550

Meter B

470

360

560

Subassembly D

270

250

320

data. Exhibit 9.9 shows the requirements for meters A and B and subassembly D for a

three-month period (months three through five). There are some “other parts” used to make

the meters. In order to keep our example manageable, we are not including them in this

example.

Developing a Master Production Schedule

For the meter and component requirements specified in Exhibit 9.9, assume that the quantities

to satisfy the known and random demands must be available during the first week of

the month. This assumption is reasonable because management (in our example) prefers to

produce meters in a single batch each month rather than a number of batches throughout

the month.

Exhibit 9.10 shows the trial master schedule that we use under these conditions, with

demand for months 3, 4, and 5 listed in the first week of each month, or as weeks 9, 13,

and 17. For brevity, we will work with demand through week 9. The schedule we develop

should be examined for resource availability, capacity availability, and so on, and then

revised and run again. We will stop with our example at the end of this one schedule,

however.

Bill-of-Materials (Product Structure)

The product structure for meters A and B is shown in Exhibit 9.11A in the typical way

using low-level coding, in which each item is placed at the lowest level at which it appears

in the structure hierarchy. Meters A and B consist of a common subassembly C and some

parts that include part D. To keep things simple, we will focus on only one of the parts,

part D, which is a transformer.

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!