<str<strong>on</strong>g>Quarterly</str<strong>on</strong>g> <strong>Progress</strong> <str<strong>on</strong>g>Report</str<strong>on</strong>g><br />
2/16/2010 - Yes 3/7/2011 - Yes 11/28/2011 - Yes<br />
<strong>Progress</strong> & Significant Results This Quarter:<br />
Task 1: Literature Review:<br />
This task is completed<br />
Task 2: Experimental Program Development:<br />
This task is completed<br />
Task 3: Lab Testing:<br />
-Mixture level tests were c<strong>on</strong>ducted for Lime Dry and Wet techniques.<br />
-Mixture level tests were c<strong>on</strong>ducted for all plant mixes.<br />
-No correlati<strong>on</strong> was identified between the results of lab and plant mixes. This could be due to insufficient aging of lab mixes. Further evaluati<strong>on</strong> of<br />
the causes will be investigated.<br />
Task 4: C<strong>on</strong>structi<strong>on</strong> & ATLAS Testing:<br />
Foamed N90 and Foamed N90 with liquid antistrip secti<strong>on</strong>s are still being tested under accelerated testing (using ATLAS). 240,000 cycles were<br />
completed <strong>on</strong> the foamed secti<strong>on</strong> without significant rutting, while the total number of cycles applied <strong>on</strong> the foamed with liquid antistrip secti<strong>on</strong> is<br />
currently at 160,000 cycles; rutting started to appear.<br />
Task 5: Final <str<strong>on</strong>g>Report</str<strong>on</strong>g><br />
First draft of lab report is ready and edited.<br />
Anticipated Work Next Quarter:<br />
Task 3: Lab Testing:<br />
-Complete tests of N90 mixes.<br />
-Run DSR and adhesi<strong>on</strong> tests <strong>on</strong> the mixture binder.<br />
-Extracti<strong>on</strong> of N90 cored c<strong>on</strong>trol mix samples<br />
Task 4: C<strong>on</strong>structi<strong>on</strong> & ATLAS Testing:<br />
-C<strong>on</strong>tinue running ATLAS over the foamed with liquid antistrip secti<strong>on</strong> until significant rutting is measured. Then moving ATLAS to the liquid<br />
antistrip and lime secti<strong>on</strong>s.<br />
Project Impediments & Recommended Soluti<strong>on</strong>s:<br />
Task 4: C<strong>on</strong>structi<strong>on</strong> & ATLAS Testing:<br />
The main imedipemt is the high unexpected number of loading cycles of test secti<strong>on</strong>s to obtain significant rutting. This could cause an unavoidable<br />
delay in the project delivery.<br />
Deliverables and Implementati<strong>on</strong> Strategy:<br />
Last Updated: 5/16/2012<br />
Approved By TRP Chair: 5/16/2012<br />