Project Title: Evaluating of Traffic Flow M<strong>on</strong>itoring Technologies: Cicero-<br />
Midway Smart Corridor Case Study<br />
QPR Author Name: Jakob Erikss<strong>on</strong><br />
Teleph<strong>on</strong>e: 312-996-0481 Project Completed: 99.9%<br />
Percent Time Used to Date: 200 %<br />
<strong>Research</strong> <str<strong>on</strong>g>Quarterly</str<strong>on</strong>g> <strong>Progress</strong><br />
<str<strong>on</strong>g>Report</str<strong>on</strong>g><br />
Ending MARCH 2012<br />
Last Updated: 6/18/2012 <str<strong>on</strong>g>Report</str<strong>on</strong>g> Generated:6/27/2012<br />
TRP Chair Approved:<br />
Project Number: R27-91 Functi<strong>on</strong> Code: R27-91<br />
Estimated Dates<br />
Fiscal Year: 2012<br />
Project Status: Behind<br />
Schedule (red)<br />
Task Title Start Complete <strong>Progress</strong> this<br />
Quarter<br />
Completed<br />
Task 1: Identify data sources, experimental design 1/1/2010 12/31/2010 No Yes<br />
Task 2: Set up and test data-collecti<strong>on</strong> 4/1/2010 12/31/2010 No Yes<br />
Task 3: Data collecti<strong>on</strong> 7/1/2010 12/31/2010 No Yes<br />
Task 4: Data analysis 10/1/2010 4/1/2011 No Yes<br />
Task 5: Final <str<strong>on</strong>g>Report</str<strong>on</strong>g> 4/1/2011 5/1/2011 No Yes<br />
Project Start Date: 1/1/2010 Original Project End Date: Number of Extenti<strong>on</strong>s: 0 Current Project End Date: 12/31/2010<br />
Original Project Budget: $100000 Number of Budget Changes: 0 Current Project Budget: $99938<br />
Total Funds Expended this Quarter: $0 Total Project Expenses to Date: $0 Total % Of Budget Spent To Date: 0%<br />
Project Descripti<strong>on</strong>:<br />
Collecti<strong>on</strong> of probe-vehicle and sensor data in the regi<strong>on</strong> of interest, cleaning and map-matching of said data. Evaluati<strong>on</strong> of accuracy of multiple<br />
technologies either through direct comparis<strong>on</strong> with ground truth (probe vehicles) when data is available, or through simulati<strong>on</strong> where direct<br />
measurement data is unavailable.<br />
Keywords: traffic flow, Cicero-Midway, corridor, arterial streets<br />
Principal Investigator:<br />
Name: Jakob Erikss<strong>on</strong> Organizati<strong>on</strong> / Address<br />
Teleph<strong>on</strong>e: 312-996-0481<br />
Email: jakob@uic.edu<br />
UIC<br />
University of <strong>Illinois</strong> at Chicago Dept. Computer Science Room 1120 SEO (M/C 152) Chicago, IL 60607<br />
<strong>Research</strong> Student Team Members: Balakrishnan Radhakrishnan (primary)<br />
Technical Review Panel:<br />
Members Teleph<strong>on</strong>e Email Address<br />
Jeff Gallas (Chair) 708-524-2145 jeff.galas@illinois.gov<br />
Abraham Emmanuel Abraham Emmanuel<br />
David Zavattero David Zavattero<br />
Meeting Dates - Minutes Available?<br />
2/10/2010 - No 4/29/2010 - No 5/4/2010 - No 5/14/2010 - No<br />
<strong>Progress</strong> & Significant Results This Quarter:<br />
The PI sent the draft report to ICT for editing in April 2011. ICT edited the report and sent the report to the TRP Chair in May 2011 for<br />
review/approval.<br />