• The VIK component offered by international broadcasters<br />
could have been negotiated towards increasing the cash<br />
component. Rate Cards could have been obtained from<br />
the broadcasters and in case the OC CWG Delhi 2010<br />
required Free Commercial Time on their channels, it could<br />
have been purchased and paid for.<br />
VENUE DEVELOPMENT, OVERLAYS<br />
AND OPERATIONS<br />
Venue Development: Responsible for integration with<br />
external agencies/stakeholders like Venue Owners and other<br />
governmental departments and formulation of Venue Use<br />
Agreements.<br />
Overlays: Responsible for the development of venues in<br />
accordance with venue briefs duly assisted by consultants,<br />
preparation of Bill of Quantity with respect to <strong>Games</strong> Time<br />
requirement of Overlays and their subsequent procurement and<br />
deployment at venues.<br />
Venue Operations: The centre of gravity of the planning<br />
process at the OC CWG Delhi 2010, interface between FAs<br />
and the lead agency in the planning process.<br />
The FA had to face many challenges in terms of limited<br />
resources of experienced manpower, late possession of venues,<br />
venues being incomplete (some of them till end September<br />
2010), several agencies working simultaneously to get their<br />
jobs completed, coordination and accreditation issues, heavy<br />
rains in August/September 2010, changes proposed by the<br />
Security agencies and other FAs. It successfully acted as a key<br />
coordinator between the Venue Owners and different FAs,<br />
stakeholders, venue teams and was also able to cater to last<br />
minute requirements that came from different sources.<br />
The venue teams were moved into the venues,<br />
venues readiness and operational planning finalised,<br />
ensuring smooth and problem free conduct of 12 days<br />
of sport extravaganza from 3 to 14 October 2010.<br />
The diesel generator sets used for the Opening and<br />
Closing Ceremonies and Broadcast compounds provided<br />
114<br />