Project B: 20 kW Grid C<strong>on</strong>nected Solar PV<br />
Purposes:<br />
To dem<strong>on</strong>strate the technology and obtain experiences with<br />
the operati<strong>on</strong> under <strong>Oman</strong>i c<strong>on</strong>diti<strong>on</strong>s. The results of this<br />
project could be used as a basis <strong>for</strong> the design of larger PV<br />
projects. We recommend undertaking a number of small scale<br />
projects <strong>for</strong> different types of applicati<strong>on</strong>s: <strong>on</strong> buildings, parking<br />
areas etc.<br />
Technology: 20 kW system c<strong>on</strong>sisting of 20 kWp solar PV panels (app. 200<br />
m 2 ) and a 20 kW power c<strong>on</strong>verter.<br />
Locati<strong>on</strong>:<br />
Annual energy output :<br />
Budget:<br />
<strong>Energy</strong> producti<strong>on</strong> cost:<br />
Rural area, c<strong>on</strong>nected to local grid/power system.<br />
34 MWh/year<br />
USD 150,000 (tentative)<br />
425 USD/MWh<br />
Be<strong>for</strong>e implementing these types of projects, we recommend further detailed<br />
technical and ec<strong>on</strong>omic analysis is undertaken to verify assumpti<strong>on</strong>s in this report<br />
and c<strong>on</strong>firm the suitability of individual project locati<strong>on</strong>s.<br />
We also recommend the implementati<strong>on</strong> of a wind m<strong>on</strong>itoring programme in<br />
south <strong>Oman</strong> al<strong>on</strong>g the coast and in the mountains north of Salalah to verify and<br />
map wind energy resources. This programme should also include detailed grid<br />
analysis to determine the amount of wind turbine capacity that could be c<strong>on</strong>nected<br />
to the Salalah Power System (noting that <strong>for</strong> technical reas<strong>on</strong>s wind turbine<br />
capacity should normally not exceed 15% to 20% of total system capacity).<br />
We expect the wind m<strong>on</strong>itoring programme to support the early implementati<strong>on</strong><br />
of a wind turbine project such as Project C.<br />
Project C: 10 MW Grid C<strong>on</strong>nected Wind Farm<br />
Purposes:<br />
Technology:<br />
Locati<strong>on</strong>:<br />
Annual energy output:<br />
Budget:<br />
<strong>Energy</strong> producti<strong>on</strong> cost:<br />
Dem<strong>on</strong>strate the technology and obtain experience of operating<br />
the technology under <strong>Oman</strong>i c<strong>on</strong>diti<strong>on</strong>s.<br />
10 MW Wind farm c<strong>on</strong>sisting of 5 x 2 MW wind turbines.<br />
Dhofar, Thumrait/Quiro<strong>on</strong> Hariti area.<br />
25-30 GWh/year.<br />
USD 20 - 22 mill. (tentative)<br />
65 USD/MWh.<br />