Chapter 1 PUMPING INSTALLATION<br />

Fig. 1.13 Crane General Arrangement<br />

c) Stoplog<br />

Stoplog grooves are provided ahead of the trash racks for purpose of maintenance <strong>and</strong> repair work.<br />

Stainless steel side seal plates or mild steel guides are fixed to the grooves so that the stoplog<br />

elements are properly guided into the slots.<br />

Normally stoplog is made up of three (3) to five (5) pieces of mild steel panels to the required height<br />

to block out the water from entering the approach channel. Decision of the number of elements is<br />

governed by the admissible space available <strong>and</strong> the limitation of the lifting effort. Each panel shall<br />

be limited to less than 2000 kg so that it can be easily h<strong>and</strong>led with a light duty lifting device or<br />

lorry-mounted crane. Side rollers are provided to facilitate easy insertion of the element. The stoplog<br />

is normally designed for balanced condition, but main rollers may be required if unbalanced condition<br />

prevails. Effective sealing is accomplished with the combination of seal seals <strong>and</strong> bottom seal to each<br />

element. Design of the lifting device shall be capable of being self-engaged <strong>and</strong> released easily to<br />

the lifting bracket of the stoplog element.<br />

General arrangement, construction <strong>and</strong> dimensional requirement of the stoplog elements are as<br />

shown in Fig. 1.14.<br />