Chapter 1 PUMPING INSTALLATION<br />
d) Generating Set<br />
For reliable operation, sometimes generating set is installed to provide back-up electrical power<br />
supply in the event of TNB outage. Depending on the severity of the consequences, generating set<br />
is provided mainly for flood mitigation project. Compliance to Jabatan Alam Sekitar requirement is<br />
warranted for the installation of the generating set. Chargeman of the appropriate grade should be<br />
assigned to look after the gen-set operation.<br />
1.14 INSTALLATION WORKS<br />
Installation works needs to be treated with care as equipment damage, malfunction <strong>and</strong> operating<br />
problems would result if it were not properly installed. Ensure that method statement, which details<br />
how the work is to be done, is readily available <strong>and</strong> is being adhered accordingly. Assign skilled <strong>and</strong><br />
trained craftsman, equip with adequate <strong>and</strong> proper tools <strong>and</strong> equipment, <strong>and</strong> maintain good current<br />
engineering practices in the execution of the work. Ensure that safety precautions are being<br />
implemented <strong>and</strong> safety rules are being closely observed.<br />
1.15 TESTING AND COMMISSIONING OF PUMPING SYSTEM<br />
Plants <strong>and</strong> equipment are subject to testing <strong>and</strong> commissioning before being turned over to the user.<br />
The purpose of the testing <strong>and</strong> commissioning is to make sure that all equipment <strong>and</strong> systems not<br />
only are functional <strong>and</strong> operational but also meet the performance requirements. Testing should be<br />
properly planned <strong>and</strong> executed in order to avoid unnecessary delay at site. All parties involved shall<br />
be closely coordinated, <strong>and</strong> systematic approach to the testing shall be adapted with clear written<br />
instructions <strong>and</strong> test records.<br />
Pre-start Checks<br />
To begin with, inspect the equipment in accordance with the manufacturer’s submittals to confirm<br />
correct equipment is installed. The inspection team comprising all the related parties shall verify the<br />
proper installation, <strong>and</strong> supervise any adjustments <strong>and</strong> installation checks. Having satisfied with the<br />
equipment installation status, an official report shall be accompanied certifying that the equipment is<br />
properly installed <strong>and</strong> is ready to operate.<br />
<strong>Electrical</strong> Systems <strong>–</strong> Energizing<br />
Upon completion of the pre-start checks above, conduct a thorough <strong>and</strong> complete examination of the<br />
electrical system before start-up the system. The electrical system including all electrical components<br />
are checked, adjusted <strong>and</strong> tested accordingly, <strong>and</strong> all protective devices are calibrated with the<br />
recommended settings. It is important that all electrical checks be conducted in the presence of<br />
qualified <strong>and</strong> competent electrical inspectors. Turn on the power for the electrical system as soon as<br />
all the necessary electrical checks are fulfilled. A full test report of the above-mentioned electrical<br />
checks/test is prepared.<br />
Equipment Start-up<br />
Upon completion of the electrical checks above, the whole plant is then scheduled for start-up. The<br />
whole system will be put on operational checks to ensure that it is fully functional <strong>and</strong> operational<br />
without any major problems. Monitor the running conditions of the equipment during the test run,<br />
adjust <strong>and</strong> rectify faults <strong>and</strong> malfunctions encountered.<br />