Rail Corporation New South Wales<br />

<strong>Rolling</strong> <strong>Stock</strong> <strong>PPP</strong> – <strong>Double</strong> <strong>Deck</strong> <strong>Trains</strong><br />

Maintenance Facility Works Specification<br />

<strong>Exhibit</strong> 7 - MFS v7.doc<br />

Signalling work. Once defined, <strong>PPP</strong> Co shall treat this as a <strong>RailCorp</strong> Initiated<br />

Variation in accordance with the Contract.<br />

3.1.6 Overhead Traction Power System<br />

<strong>PPP</strong> Co must design, construct and commission all aspects of the Overhead Traction<br />

Power System for the Site Trackwork constructed as part of the Site Works. The scope of<br />

this work must include:<br />

(a) design, supply and installation of all supporting structures, including any<br />

foundations required;<br />

(b) design, supply and installation of the Overhead Wires, suspension system, and<br />

insulators; and<br />

(c) design, supply and installation of the controls and switchgear, including safety<br />

isolation arrangements, procedures and documentation to the standards listed<br />

in Attachment 3.<br />

<strong>PPP</strong> Co must provide Overhead Traction Power System for the Car Turning Loop,<br />

sufficient to power a 192m long train along the Car Turning Loop so that the trailing end of<br />

the train is at least 20m clear of the associated points.<br />

<strong>PPP</strong> Co must calculate the power draw required from the Overhead Traction Power<br />

System for the Maintenance Facility. <strong>PPP</strong> Co must provide this information to <strong>RailCorp</strong> to<br />

enable finalisation of the design of the power feed from the overhead traction power<br />

substation being provided by <strong>RailCorp</strong>. The calculation must include the power required for<br />

any Sets or Other Sets in the Maintenance Facility and on the Car Turning Loop.<br />

3.1.7 Car Parking, Roadways and Pedestrian Walkways<br />

<strong>PPP</strong> Co must design, construct and commission the car parking, roadways, drainage and<br />

pedestrian walkways for accessing the Building and for general movement(s) within the<br />

Maintenance Site.<br />

The car parking must consist of a sealed car park capable of accommodating car numbers<br />

commensurate with the planned staffing levels of <strong>PPP</strong> Co and <strong>RailCorp</strong> staff numbers. For<br />

the purpose of this clause, the car numbers commensurate with <strong>RailCorp</strong> staff numbers is<br />

sixty (60), consisting of twenty (20) crew members in each of two shifts, plus twenty (20)<br />

others at any given time. The car park is to be kerbed, guttered, parking spaces linemarked,<br />

illuminated, and appropriately drained.<br />

The car parking must be designed to comply with the requirements of people with<br />

disabilities and conform with Australian Standard AS 1428 Part 2 Enhanced and Additional<br />

Requirements – Buildings and Facilities.<br />

The roadways must consist of sealed heavy-duty pavements suitable for articulated heavy<br />

vehicles. The scope of work must include all signage necessary for road vehicle<br />

movements (including maximum speed signs, stop signs etc) and a pedestrian pathway<br />

accessing the Maintenance Site from the street. The truck access to the Maintenance Site<br />

is proposed to be at-grade from Manchester Road North. The road should involve the<br />

v7 – 17/01/2011 Page 15 of 51