RFTA<br />

00374<br />

RAIL CORPORATION NEW SOUTH WALES<br />

ROLLING STOCK <strong>PPP</strong> – DOUBLE DECK TRAINS<br />

MAINTENANCE FACILITY SPECIFICATION - ATTACHMENT 7<br />

ATTACHMENT 7 - SIGNAL FUNCTIONAL SPEC V7.DOC<br />

to be provided where required to ensure that the overall signalling / control system<br />

operates reliably.<br />

• Visual “normal” and “backup” power status and alarm indications are required. These<br />

indications are to be displayed locally at each supply location and remotely, on the<br />

Controller’s control panel, at the Control Centre<br />

10.3.6 SIGNALLING TELEPHONES<br />

Telephone requirements are shown in the table below:<br />

Location Telephone Requirements<br />

At Signals No telephone required<br />

At motorised Points No telephone required<br />

At Ground Frame operated points A telephone, located adjacent to the points, with<br />

a direct connection to the <strong>PPP</strong> Yard Control is<br />

required<br />

10.3.7 CONTROL SYSTEM<br />

10.3.7.1 Location<br />

A new computer based control system, provided by <strong>PPP</strong> Co., is required to control and<br />

monitor all train movements within the signalled areas of the <strong>PPP</strong> Yard Area and across the<br />

various interfaces with the <strong>RailCorp</strong> Network.<br />

The control system will be operated from a Control Room to be strategically located within<br />

the Yard Area so as to allow the Yard Controller to see as much of the Yard as possible.<br />

It is proposed that the Yard Control will be in operation 24 hours a day, 7 days a week.<br />

10.3.7.2 Key Requirements and Functionality<br />

The control system must be in accordance with <strong>RailCorp</strong> standards and meet the following<br />

key requirements / functionality:<br />

• Reliability / Availability<br />

• Operator Interface<br />

• Cover the required control area<br />

• Train Describer facilities (For Arriving / Departing Services)<br />

• Automatic Train Reporting (ATR) facilities (For Arriving / Departing Services)<br />

• Electronic data logging and replay of all inputs and outputs.<br />

• Interface to relevant <strong>RailCorp</strong> train control systems<br />

01/09/2010 – v7 Page 27 of 40