RAIL CORPORATION NEW SOUTH WALES<br />

10.3.7.3 Reliability / Availability<br />

ROLLING STOCK <strong>PPP</strong> – DOUBLE DECK TRAINS<br />

MAINTENANCE FACILITY SPECIFICATION - ATTACHMENT 7<br />

ATTACHMENT 7 - SIGNAL FUNCTIONAL SPEC V7.DOC<br />

The control system must consist of a duplicated computer-based VDU (Visual Display Unit)<br />

system with automatic changeover (Hot Standby) facilities – to switch between computers in<br />

the event of one computer failing.<br />

The changeover between systems shall not affect availability of the overall signalling<br />

system.<br />

10.3.7.4 Operator Interface<br />

The Train Control System must have operator input controls and screen displays based on<br />

<strong>RailCorp</strong> standards. LCD wide-screen displays to be provided for the controller’s<br />

workstation.<br />

The control system must be capable of controlling and displaying, over the control area, the<br />

following:<br />

Item Control Display<br />

<strong>Trains</strong> operating within the <strong>PPP</strong> Yard Area Yes Yes<br />

<strong>Trains</strong> entering / leaving the <strong>PPP</strong> Yard Area<br />

at the interfaces with the adjacent <strong>RailCorp</strong><br />

network<br />

<strong>Trains</strong> approaching (on the <strong>RailCorp</strong> lines)<br />

the interfaces between the <strong>PPP</strong> Yard Area<br />

& <strong>RailCorp</strong> network<br />

Yes (Dual control in conjunction<br />

with the relevant <strong>RailCorp</strong><br />

signaller)<br />

01/09/2010 – v7 Page 28 of 40<br />

Yes<br />

No (Under <strong>RailCorp</strong> control) Yes<br />

Notes: The exact requirements for the control of signal routes, for all stages, are detailed in<br />

section 9.3.6<br />

The information displayed by the control system to the controller must provide all the<br />

information covered in the standards, including the following:<br />

Item Comment<br />

Train location Track circuit occupancy – individual track<br />

circuit resolution is required<br />

Train Identification Train Description required for trains standing<br />

at Departure signals waiting for clearance to<br />

enter the <strong>RailCorp</strong> network. (Train<br />

Description required for trains entering the<br />

<strong>PPP</strong> Yard from the <strong>RailCorp</strong> network - Stage<br />

3 only)