RAIL CORPORATION NEW SOUTH WALES<br />
12 CONSTRUCTION<br />
12.1 GENERAL<br />
ROLLING STOCK <strong>PPP</strong> – DOUBLE DECK TRAINS<br />
MAINTENANCE FACILITY SPECIFICATION - ATTACHMENT 7<br />
ATTACHMENT 7 - SIGNAL FUNCTIONAL SPEC V7.DOC<br />
The Signalling must be in accordance with <strong>RailCorp</strong> standards for Signalling, and<br />
Communications systems.<br />
All materials used must meet the requirements set out in the relevant <strong>RailCorp</strong> standards.<br />
See the <strong>RailCorp</strong> website for details of the latest standards.<br />
Where there is no specific <strong>RailCorp</strong> standard the relevant Australian standards apply.<br />
12.2 CONSTRUCTION AREAS<br />
The relevant <strong>RailCorp</strong> and <strong>PPP</strong> Co. construction areas and responsibilities are shown in<br />
colour on a version of the signalling schematic drawings.<br />
The Concept Signalling requirements showing the Construction Areas for each of the stages<br />
are shown on the following A3 drawings:<br />
Stages 1 & 2 – Construction Areas SG0405311 (Sheet 1) To SG0405317 (Sheet 7)<br />
Stages 3 – Construction Areas SG0405318 (Sheet 1) To SG0405324 (Sheet 7)<br />
Copies of these drawings are included as Attachments 3 & 4 respectively<br />
12.3 SPECIFIC REQUIREMENTS<br />
Provision must be made for the Interfaces to the <strong>RailCorp</strong> network – including <strong>RailCorp</strong>’s<br />
control of all trains entering the By Pass 1, Arrival 1, Arrival 2 and Commissioning<br />
Track/Down Relief during stage 1 as detailed on the attached signalling drawings.<br />
Provision must also be made during the construction of Stage 1 for the requirements of<br />
Stages 2 & 3.<br />
These requirements include:<br />
• All cable routes, underline crossings and pits<br />
• All conduits including spares<br />
• Buildings<br />
• Location cases<br />
• Power supplies<br />
• Interfaces to the <strong>RailCorp</strong> network<br />
• Suitable method of access by <strong>RailCorp</strong> personnel<br />