RAIL CORPORATION NEW SOUTH WALES<br />
2 OVERVIEW<br />
2.1 KEY ELEMENTS OF THE FACILITY<br />
ROLLING STOCK <strong>PPP</strong> – DOUBLE DECK TRAINS<br />
MAINTENANCE FACILITY SPECIFICATION - ATTACHMENT 7<br />
ATTACHMENT 7 - SIGNAL FUNCTIONAL SPEC V7.DOC<br />
The proposed <strong>PPP</strong> Maintenance Facility is south of the existing western Main Line and<br />
Down Relief between 18.900 km and 20.5km.<br />
Key elements of the <strong>PPP</strong> Facility include:<br />
• A Maintenance Building with maintenance roads.<br />
• Storage Roads (for storage of sets, hand over and pick up, driver's preparation and<br />
minor repairs).<br />
• Standing Roads east and west of the Maintenance Building (trains entering/leaving<br />
Maintenance Building, cleaning if not done in Building, Graffiti removal, minor repairs<br />
and driver’s preparation).<br />
• Underfloor Wheel Profiling Plant (UWPP) Facility.<br />
• Train Washplant Facility.<br />
• A Bypass road around the facility.<br />
• Car Turning Loop road around MainTrain.<br />
The Down Relief is an important interface for the <strong>PPP</strong> Maintenance Facility. It extends<br />
between the Main Line access point at the existing No.53 crossover at Auburn and No.705<br />
crossover at Clyde. It is to be upgraded by <strong>RailCorp</strong> (under a separate project).<br />
Existing turnouts No.49 and No.52 on the Down Relief at the Auburn end of the site are to<br />
remain and be used as key entry points to the <strong>PPP</strong> Maintenance Facility. <strong>RailCorp</strong> is to<br />
upgrade the Down Relief in accordance with the Enabling Works specification that will<br />
provide access to the <strong>PPP</strong> Site from the Granville and Auburn ends<br />
Access between the <strong>PPP</strong> Maintenance Facility and the <strong>RailCorp</strong> network will also be<br />
provided by new crossovers joining the Down Relief at approximately 20+050km (known as<br />
Clyburn Junction).<br />
01/09/2010 – v7 Page 5 of 40