Public Involvement/Project Coordination October 2005<br />
Comment: Would like to see a bridge over the railroad tracks.<br />
Response: A grade-separated railroad crossing is part of the proposed improvements<br />
(see Chapter 3, Preferred Alternative, page 3-11).<br />
Comment: What are the predicted traffic volumes for <strong>Twin</strong> <strong>Peaks</strong> Road and the<br />
interchange?<br />
Response: According to the <strong>Traffic</strong> Report, 21,<strong>10</strong>0 vehicles per day and 28,900 vehicles<br />
per day would use <strong>Twin</strong> <strong>Peaks</strong> Road west and east of the interchange by the year 2030,<br />
respectively.<br />
Comment: Will the design concept coordinate with the DeAnza Trail?<br />
Response: Yes, the DeAnza Trail would cross beneath the <strong>Twin</strong> <strong>Peaks</strong> Road bridges<br />
over the Santa Cruz River. The bridge would be of sufficient height to allow equestrians<br />
to pass beneath the bridges (see Chapter 3, Preferred Alternative, page 3-11).<br />
Comment: Will the traffic volumes take into account the new Continental Reserve<br />
development?<br />
Response: Yes, the traffic projections provided for this project include planned growth<br />
in employment and population in the entire area through the year 2030.<br />
Comment: Will there be sound walls along <strong>Twin</strong> <strong>Peaks</strong> Road?<br />
Response: The traffic noise analysis recommended sound walls only along the west side<br />
of Continental Ranch south of <strong>Twin</strong> <strong>Peaks</strong> Road. The existing privacy walls along <strong>Twin</strong><br />
<strong>Peaks</strong> Road are effective at mitigating traffic noise (see Chapter 4, Noise Section, page<br />
4-49).<br />
Comment: Why does the process take so long? Can design be done during the planning<br />
process to speed things up?<br />
Response: This project would utilize federal funds and must follow the federal process;<br />
therefore, final design may not proceed until after the environmental documentation is<br />
completed.<br />
Comment: What about widening some of the other roads, like Silverbell from Cortaro to<br />
Ina?<br />
Response: Silverbell Road from Cortaro Road to Ina Road is anticipated to be<br />
constructed and widened prior to the completion of this project; however, widening<br />
other roads does not accomplish the project’s established purpose and need (see<br />
Chapter 2, Project Need, page 2-2).<br />
Comment: How will we get in and out of Sunflower, if <strong>Twin</strong> <strong>Peaks</strong> is extended and<br />
becomes busier?<br />
Response: <strong>Traffic</strong> signals are proposed at the intersections of <strong>Twin</strong> <strong>Peaks</strong><br />
Road/Coachline Road and <strong>Twin</strong> <strong>Peaks</strong> Road/Access Roads; therefore, the signals would<br />
produce gaps in traffic needed to cross the traffic lanes. The existing median opening at<br />
Sunflower Ridge Road would remain also, providing a storage area for turning vehicles.<br />
Interstate <strong>10</strong> <strong>Traffic</strong> <strong>Interchange</strong> at<br />
<strong>Twin</strong> <strong>Peaks</strong>/Linda Vista<br />
5-4<br />
Project No.: NH-0<strong>10</strong>-D (AIW)<br />
TRACS No.: <strong>10</strong> PM 236 H5838 01D