Mastering Different Fields <strong>of</strong> Civil Engineering Works (VC-Q&A Method) Vincent T. H. CHU<br />

suction hopper dredgers are mounted with draghead or dragarm pumps<br />

which increases the dredging depth and trims down the occurrence <strong>of</strong><br />

cavitation as suggested by John B. Herbioh (1992). This machine is limited<br />

to dredging relatively low-strength material. Moreover, they cannot be<br />

deployed in very shallow waters and instead grab dredgers should be used.<br />

However, its dredging capacity is higher than that <strong>of</strong> grab dredger and it<br />

can be mobilized in relatively deep-water region.<br />

Trailer suction hopper dredgers are renowned for their mobility, versatility<br />

and capability to operate in unfavorable sea conditions.<br />

3. What is the purpose <strong>of</strong> formation <strong>of</strong> bunds in reclamation? (R1)<br />

Reclamation works normally proceed behind the seawall to protect against<br />

typhoon attack. In case where s<strong>of</strong>t marine mud is encountered during<br />

reclamation, bunds may be formed on planned alignment <strong>of</strong> road and<br />

drainage works and locations <strong>of</strong> early development to displace mud to<br />

other less important areas should mudwaves indeed occur. Reclamation<br />

may be carried out in strips or even crossed bunds forming a grid. Hence, if<br />

mudwaves really occur, they could be isolated and dealt with individually.<br />

4. In case mud waves occur during reclamation, what are the possible<br />

solutions to rectify the situation? (R2)<br />

(i) Option 1 – Complete Removal <strong>of</strong> All Disturbed Mud<br />

To remove all disturbed mud once mud waves occur is the fastest way to<br />

treat the problem. After that, filling material is used for replacing the<br />

disturbed mud. However, this option is a rather expensive option because it<br />

involves dredging <strong>of</strong> all disturbed mud and replacement <strong>of</strong> large amount <strong>of</strong><br />

fill.<br />

(ii) Option 2 – Accelerated consolidation <strong>of</strong> Disturbed Mud<br />

This option involves placement <strong>of</strong> surcharging loads on top <strong>of</strong> mud waves,<br />

together with installation <strong>of</strong> band drains to accelerate the consolidation <strong>of</strong><br />

disturbed mud. This method suffers from the drawback that sufficient long<br />

time is required for the consolidation process <strong>of</strong> mud.<br />

(iii) Option 3 – Partial Removal <strong>of</strong> Disturbed Mud<br />

This option is a combination <strong>of</strong> the first two options in which the top weak<br />

layer <strong>of</strong> mud is removed while the lower mud is treated with surcharging<br />

with band drain installation.<br />