A <strong>Self</strong>-<strong>Learning</strong> <strong>Manual</strong><br />

Mastering Different Fields <strong>of</strong> Civil Engineering Works (VC-Q&A Method) Vincent T. H. CHU<br />

any claims <strong>of</strong> cost which is the main concern for most engineers. This is<br />

the contractual power given to the Engineer in case <strong>of</strong> any failure in tests<br />

required by the contract, even though some engineers argue that slump<br />

tests are not as important as other tests like compression test.<br />

The second school <strong>of</strong> thought is to let the contractor to continue their<br />

concreting works and later on request the contractor to prove that the<br />

finished works comply with other contractual requirements e.g.<br />

compression test. This is based upon the belief that workability is mainly<br />

required to achieve design concrete compression strength. In case the<br />

compression test also fails, the contractor should demolish and reconstruct<br />

the works accordingly. In fact, this is a rather passive way <strong>of</strong> treating<br />

construction works and is not recommended because <strong>of</strong> the following<br />

reasons:<br />

(i) Workability <strong>of</strong> freshly placed concrete is related not only to strength<br />

but also to durability <strong>of</strong> concrete. Even if the future compression test<br />

passes, failing in slump test indicates that it may have adverse<br />

impact to durability <strong>of</strong> completed concrete structures.<br />

(ii) In case the compression test fails, the contractor has to deploy extra<br />

time and resources to remove the work and reconstruct them once<br />

again and this slows down the progress <strong>of</strong> works significantly.<br />

Hence, in view <strong>of</strong> such likely probability <strong>of</strong> occurrence, why<br />

shouldn’t the Engineer exercise his power to stop the contractor and<br />

save these extra time and cost?<br />

91