A <strong>Self</strong>-<strong>Learning</strong> <strong>Manual</strong><br />

Mastering Different Fields <strong>of</strong> Civil Engineering Works (VC-Q&A Method) Vincent T. H. CHU<br />

(i) The rate <strong>of</strong> installation <strong>of</strong> prefabricated band drains is high. As such,<br />

substantial cost and time could be saved by using this method <strong>of</strong><br />

construction.<br />

(ii) The disturbance <strong>of</strong> soil during installation <strong>of</strong> drains is smaller when<br />

using prefabricated band drains.<br />

(iii) The ease <strong>of</strong> fabrication, quality control and storage associated with<br />

band drains.<br />

14. What are the potential problems <strong>of</strong> smear around vertical drains?<br />

(R8)<br />

Smear zones are generated during the installation <strong>of</strong> vertical drains in<br />

which the zone <strong>of</strong> soils surrounding the band drains are disturbed. Soils in<br />

the smear zones are remoulded during the installation process and the<br />

effectiveness <strong>of</strong> band drains is reduced. For instance, the compressibility <strong>of</strong><br />

surrounding soils is increased and this brings about the reduction <strong>of</strong> their<br />

permeability. In essence, with the reduced permeability <strong>of</strong> soils around<br />

band drains, it takes longer time to complete the consolidation process.<br />

To prevent the formation <strong>of</strong> smear zones, the raising and lowering <strong>of</strong><br />

mandrel during drain installation should be minimized. Moreover, soil<br />

disturbance can be controlled by avoiding the use <strong>of</strong> vibratory hammers<br />

which serve to drive the drains into the ground [35].<br />

Fig. Smear zones in band drain<br />

15. For drained reclamation, what is the significance <strong>of</strong> smear zone<br />

induced by installation <strong>of</strong> band drains? (R8)<br />

During installation <strong>of</strong> band drains, smear zones are created in which a<br />