Field Application Reports<br />
Products:<br />
Application Date:<br />
Application Customer: Date:<br />
Customer: Industry:<br />
Industry:<br />
Location 87<br />
Floor Coating<br />
Floor Patch Fast Cure / Concrete Primer /<br />
Epoxy Coat 7000AR<br />
6/27/95<br />
Houston Power <strong>and</strong> Lighting<br />
Utility Power Generation<br />
Problem:<br />
This secondary containment area required repairs to cracks caused by thermal cycling <strong>and</strong> erosion. The<br />
erosion was accelerated by the occasional spilling or leaking of beach from the storage tanks.<br />
Solution:<br />
Complete floor <strong>and</strong> wall surfaces were first pressure washed to remove contaminates. Floor <strong>and</strong> wall<br />
areas were then etched using <strong>Devcon</strong>’s B-4 Citrus Acid Etch. All cracks were repaired <strong>and</strong> sealed with<br />
<strong>Devcon</strong>’s Floor Patch Fast Cure, (90 minute functional cure). Following a 1 hour partial cure of Floor<br />
Patch Fast Cure, Concrete Primer was applied to a thickness of 8 mils. Following a partial cure, (4<br />
hours), a final coat of Epoxy Coat 7000AR (Acid Resistant) was applied to a thickness of 16 mils.<br />
<strong>Devcon</strong>’s Epoxy Coat 7000AR withst<strong>and</strong>s aggressive chemical operating environments.