EPEA APPROVALS AENV SIRS 90 – 96<br />

Section 15.1<br />

response to SIR 402c and Figure 402-2 do not seem to reflect those opportunities<br />

for reclaiming overburden dumps as they are constructed.<br />

95a Clarify and confirm that no opportunities for reclaiming any areas of overburden<br />

dumps exist prior to 2031 or revise the plan as applicable.<br />

Response 95a No opportunities exist for reclaiming areas of the overburden dumps at the <strong>Pierre</strong><br />

<strong>River</strong> <strong>Mine</strong> before the end of 2029. As noted in the response to AENV SIR 92,<br />

construction of the first lift of the north overburden dump at the <strong>Pierre</strong> <strong>River</strong><br />

<strong>Mine</strong> will not be completed until after 2029 because of the diversion of<br />

overburden materials into in-pit dykes between 2018 and 2029. As soon as the<br />

first lift is completed, reclamation on the north overburden dump will begin.<br />

Question No. 96<br />

Request Volume 2, SIR Question 410a, Page 23-27.<br />

Shell indicates that care has been taken to minimize the stockpiled time of<br />

reclamation salvage materials.<br />

96a Given the large extent of disturbance and the fact that any reclamation is delayed<br />

until 2031, justify this statement.<br />

Response 96a Two mechanisms have been considered to minimize the time that reclamation<br />

salvage materials are stockpiled, bearing in mind that permanent reclamation<br />

might not be possible until 13 years after mine operations start in 2018.<br />

• Although permanent reclamation activities might not be available until 2031,<br />

the opportunity to farm salvaged soils, particularly surface soils during<br />

temporary reclamation activities will be considered for any area that might<br />

become available, such as the first lift of the north overburden disposal area.<br />

• Material balances for peat-mineral materials have been calculated for salvage<br />

and stockpiling as close as possible to the time of reclamation, to minimize<br />

the time materials are stockpiled, and to optimize opportunities for direct<br />

placement of peat. All upland soils will be salvaged and direct placed,<br />

stockpiled or farmed.<br />