MINING AND PROCESSING ERCB SIRS 3 – 38<br />

Question No. 30<br />

Section 4.1<br />

Request Volume 1, Section 3.1, Page 3-1, Table 3-1, Supplemental Information<br />

Responses; Volume 1, Section 10.1, Page 10-166, Table 218-4, Supplemental<br />

Information Responses.<br />

Table 3-1 indicates that revised data of Ore is 2,102 Mt. In Table 218-4, the<br />

sand, fines, bitumen and water from extraction sum to 2,263.8 Mt.<br />

30a Confirm the updated total ore tonnage. Update Table 3-1 or Table 218-4<br />

according to the latest information.<br />

Response 30a The mine quantities stated in the May 2009 <strong>Pierre</strong> <strong>River</strong> <strong>Mine</strong>, Supplemental<br />

Information, were updated to reflect the revised pit limits and updated block<br />

model. However, the mine production schedule and integrated tailings plan were<br />

not revised because of the small (5%) change in total mine volumes. Table 3-1<br />

(see the May 2009 <strong>Pierre</strong> <strong>River</strong> <strong>Mine</strong>, Supplemental Information, Volume 1)<br />

provided a comparison of the revised ore tonnage to the ore tonnage in the<br />

December 2007 application.<br />

Table 218-4 in the response to SIR 218 provided additional details on the tailings<br />

schedule submitted with the December 2007 <strong>Pierre</strong> <strong>River</strong> <strong>Mine</strong>, <strong>Project</strong><br />

Description, Volume 2. Therefore, it cannot be reconciled with the total mine<br />

quantities from the May 2009 <strong>Pierre</strong> <strong>River</strong> <strong>Mine</strong>, Supplemental Information. The<br />

extraction ore properties provided in Table 218-4 excludes breaker rejects.<br />

Therefore, the breaker reject tonnage of 86 Mt must be added to the extraction<br />

ore tonnes to reconcile with the 2,349 Mt of total ore reported in the <strong>Pierre</strong> <strong>River</strong><br />

<strong>Mine</strong> <strong>Project</strong> Description.<br />

Request 30b Update the following tables:<br />

i. Table 218-3: Supplemental Information Responses<br />

ii. Table 7-5: Volume 2 of the <strong>Pierre</strong> <strong>River</strong> <strong>Mine</strong> Application<br />

iii. Table 7-7: Volume 2 of the <strong>Pierre</strong> <strong>River</strong> <strong>Mine</strong> Application<br />

iv. Table 7-8: Volume 2 of the <strong>Pierre</strong> <strong>River</strong> <strong>Mine</strong> Application<br />

Response 30b The data was not re-calculated because the mine production schedule and<br />

integrated tailings plan were not updated for the <strong>Project</strong> Update, as stated in the<br />

response to ERCB SIR 30a.<br />

The general mine scheme and sequence of the development will be maintained.<br />

April 2010 Shell Canada Limited 4-29<br />

CR029