MINING AND PROCESSING ERCB SIRS 3 – 38<br />

Section 4.1<br />

<strong>Pierre</strong> <strong>River</strong> <strong>Mine</strong> Application in light of Muskeg <strong>River</strong> <strong>Mine</strong>’s challenges in<br />

meeting existing approval conditions with a similar design.<br />

Response 15b As outlined in the May 2009 <strong>Pierre</strong> <strong>River</strong> <strong>Mine</strong>, Supplemental Information,<br />

Volume 1, SIR 159, several improvements have been made to the Muskeg <strong>River</strong><br />

<strong>Mine</strong> process in recent years to significantly improve solvent losses and achieve<br />

regulatory compliance. These improvements will be applied to future designs,<br />

including the Muskeg <strong>River</strong> <strong>Mine</strong> Expansion TRSU process starting up in 2010.<br />

Shell is confident that, as design and operational experience grows, the <strong>Pierre</strong><br />

<strong>River</strong> <strong>Mine</strong> solvent losses will meet the current 4 vol/kvol requirement.<br />

Question No. 16<br />

Request Volume 1, Section 10.1, Page 10-85, Supplemental Information Responses.<br />

Shell describes their development and investment philosophy. In Volume 1,<br />

Section 1.2, Page 1-7, Supplemental Information Responses. Shell states,<br />

“Although the overall scope of Shell’s development plans for the <strong>Pierre</strong> <strong>River</strong><br />

<strong>Mine</strong> and the Jackpine <strong>Mine</strong> Expansion remain unchanged, the timing of the<br />

execution of certain approved Jackpine <strong>Mine</strong> and Muskeg <strong>River</strong> <strong>Mine</strong> facilities<br />

has required some adjustment.”<br />

16a Provide an updated integrated schedule for Jackpine <strong>Mine</strong> (JPM) Phase-1,<br />

Muskeg <strong>River</strong> <strong>Mine</strong> (MRM) debottlenecking, Muskeg <strong>River</strong> <strong>Mine</strong> Expansion<br />

(MRME), Jackpine <strong>Mine</strong> Expansion (JPME), and <strong>Pierre</strong> <strong>River</strong> <strong>Mine</strong> (PRM)<br />

projects that includes production capacity, timelines for construction,<br />

commissioning, and start-up.<br />

Response 16a For the requested information, see the response to ERCB SIR 12.<br />

Request 16b If an integrated schedule is not available, when will Shell commit to providing an<br />

integrated schedule for JPM Phase-1, MRM debottlenecking, MRME, JPME, and<br />

PRM projects that includes production capacity, timelines for construction,<br />

commissioning, and start-up?<br />

Response 16b Shell will provide updates to its plans for the Muskeg <strong>River</strong> <strong>Mine</strong> and Jackpine<br />

<strong>Mine</strong> as part of the annual reporting to the Board, or when changes to the design<br />

or operations scope necessitate the filing for amendments to the existing<br />

approvals.<br />

4-14 Shell Canada Limited April 2010<br />