29.09.2012 Views

Technology Status - NET Nowak Energie & Technologie AG

Technology Status - NET Nowak Energie & Technologie AG

Technology Status - NET Nowak Energie & Technologie AG

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

An example of a large scale power plant is described in more detail below,<br />

showing the different phases and their related costs. Costs may vary from<br />

USD 50 to 150 million for a 50-MW plant.<br />

Exploration and leasing: This phase is normally divided into site assessment,<br />

leasing and land acquisition, exploratory drilling, and well testing. In general, site<br />

assessment as well as leasing and land acquisition are low-risk activities with<br />

relatively low costs, ranging from USD 50,000 to USD 500,000. Exploratory<br />

drilling and reservoir assessment, as in the oil and gas field, are high-risk<br />

activities: if an adequate resource is not found, the entire project is cancelled. A<br />

wide range of issues must be addressed: geological data, geophysical surveys,<br />

approval process for drilling, road building, mobilising a drilling rig, well testing,<br />

and physical and chemical data collection. The cost can easily range from USD<br />

0.75 to USD 2.5 million per exploration well. The entire programme can cost from<br />

USD 3 to USD 6 million.<br />

Project development and feasibility studies: If the previous phase gives<br />

satisfactory results, a further series of activities can be carried out:<br />

compilation of a reservoir assessment report; negotiation of a power sales<br />

contract; approval of construction of wells, steam and water lines and power<br />

plant; and finalisation of design and cost/revenue estimation. The cost range<br />

is from USD 0.25 to USD 2.3 million, with the highest expenses for preconstruction<br />

permits and environmental approval.<br />

Well-field development and project finance, construction, start-up: This<br />

phase is rather complicated and time consuming. Activities like drilling and<br />

power plant construction can overlap and require careful scheduling.<br />

Construction time is only 12-16 months for the power generating plant, but<br />

well drilling (depending on the number of drilling rigs operating in parallel)<br />

can take several years. Overall well-field development for a standard 50-MW<br />

project with ten production wells, two injection wells and two reserve wells,<br />

at an average cost of USD 2 million per well (depending on depth), can reach<br />

USD 32 million. Power plant engineering, design, construction, and start-up<br />

are complicated but not unique to geothermal; the oil industry and other<br />

mining companies face similar challenges.<br />

Commercial operations and field and plant expansion: As noted earlier,<br />

geothermal plants have an availability factor of 98%, and can be operated at<br />

full load 24 hours a day with energy efficiency of about 97% for CHP and<br />

7-10% for electricity production. It is common to develop multiple power<br />

plants or subsequent units over time. However, before installing a second<br />

unit at the same site, it must be ensured that new wells will not affect the<br />

productivity of existing ones.<br />

6<br />

GEOTHERMAL POWER<br />

129

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!