STANDARD CONSTRUCTION DETAIL # 6-5<br />

Temporary Slope Pipe<br />

SLOPE PIPE WITH TRANSVERSE BERM<br />

Adapted from PennDOT RC70, April 2004<br />

NOTE: This table is intentionally blank <strong>and</strong> should be filled in by the plan preparer.<br />

Slope Pipe No.<br />

Outlet Protection<br />

Type<br />

R-size<br />

or Material<br />

The maximum distance between anchor stakes shall be 10 feet.<br />

Apron Length (ft)<br />

363-2134-008 / March 31, 2012 / Page 155<br />

Apron Width (ft)<br />

Transverse berm shall be used whenever temporary slope pipe is not located at low point.<br />

Slope pipes shall be inspected weekly <strong>and</strong> after each runoff event. Any accumulated sediment<br />

shall be removed from the inlet immediately.