Barrel/Riser <strong>Sediment</strong> Trap - This device has MODERATE sediment removal efficiency <strong>and</strong> is an<br />

ABACT for HQ watersheds but not for EV watersheds. The efficiency can be raised to HIGH,<br />

meeting ABACT for HQ <strong>and</strong> EV watersheds, by substituting a skimmer dewatering device for the<br />

perforated riser.<br />

PA DEP<br />

For traps with barrel/riser spillways, the crest of the riser should be set at the elevation at which the<br />

required 2,000 cubic feet/acre storage capacity is provided. The riser <strong>and</strong> outlet barrel should be sized<br />

to provide a discharge capacity of 1.5 cfs/acre. Recommended minimum barrel <strong>and</strong> riser diameters are<br />

contained in Table 8.1. Supporting calculations should be provided. The embankment should provide<br />

at least 12” of freeboard above the maximum design water elevation — the elevation at which the 1.5<br />

cfs/acre discharge capacity is provided. Perforations in the riser to dewater the trap should be limited<br />

to one 1” diameter hole per vertical foot of riser with the lowest perforation at the sediment storage<br />

elevation as shown in St<strong>and</strong>ard Construction Detail # 8-2.<br />

TABLE 8.1<br />

Recommended Minimum Pipe Sizes for Barrel/Riser <strong>Sediment</strong> Traps<br />

Barrel Diameter (in.) Riser Diameter (in.) Drainage Area (Acres)<br />

12 15 1<br />

New York DEC<br />

15 18 2<br />

18 21 3<br />

21 24 4<br />

21 27 5<br />

363-2134-008 / March 31, 2012 / Page 217