will be developed when required to meet demand. If actual activity does not meet or exceed the forecasted<br />

demand, implementation <strong>of</strong> the project schedule should be modified as necessary.<br />

The cost estimates associated with the <strong>Master</strong> <strong>Plan</strong> projects reflect allowances for Sponsor administration,<br />

engineering/design, construction contingencies, and construction administration. Depending on the<br />

implementation schedule, project costs will need to be escalated to account for future inflation in Phase 2<br />

and Phase 3. Recent history has shown that on average the Consumer Price Index (CPI) inflation<br />

increases by approximately 3 to 4 percent annually.<br />

Table 8.1 through Table 8.3 provides the 20-year ACIP for the <strong>Waterville</strong> <strong>Airport</strong>, organized into the<br />

following three phases:<br />

<br />

<br />

<br />

Phase 1 (0 to 5 years)<br />

Phase 2 (6 to 10 years)<br />

Phase 3 (11 to 20 years).<br />

Phase 1 Development (0 to 5 years)<br />

Phase 1 development consists <strong>of</strong> the following capital projects:<br />

1-A: Avigation Easement Acquisition (14 Parcels); Environmental Review; Phase I Tree<br />

Clearing (Approx. 25+ Acres)<br />

1-B: Runway 14-32 Reconstruction<br />

1-C: Design Only - Reconstruct Runway 5-23; Permitting for Phase II Tree Clearing<br />

1-D: Phase I - Reconstruct Runway 5-23; Phase II Tree Clearing<br />

1-E: Phase II ‐ Reconstruct Runway 5‐23<br />

1-F: Taxiway 'A' Pavement Repairs<br />

1-G: Construct SRE Building & Purchase Snow Blower<br />

Table 8.1<br />

Phase 1 (0 to 5 years) Project Cost<br />

Project Cost FAA MaineDOT <strong>Airport</strong> Other<br />

1-A: Avigation Easement Acquisition (14<br />

Parcels); Environmental Review; Phase I $565,000 $508,500 $28,250 $28,250 None<br />

Tree Clearing (Approx. 25+ Acres)<br />

1-B: Runway 14-32 Reconstruction $811,000 $729,900 $40,550 $40,550 None<br />

1-C: Design Only - Reconstruct Runway<br />

5-23; Permitting for Phase II Tree Clearing<br />

$475,000 $427,500 $23,750 $23,750 None<br />

1-D: Phase I - Reconstruct Runway 5-23;<br />

Phase II Tree Clearing<br />

$4,451,000 $4,005,900 $222,550 $222,550 None<br />

1-E: Phase II ‐ Reconstruct Runway 5‐23 $4,313,000 $3,881,700 $215,650 $215,650 None<br />

1-F: Taxiway 'A' Pavement Repairs $235,000 $211,500 $11,750 $11,750 None<br />

1-G: Construct SRE Building & Purchase<br />

Snow Blower<br />

$1,700,000 $1,530,000 $85,000 $85,000 None<br />

Total – Phase 1: $12,550,000 $11,295,000 $627,500 $627,500 $0<br />

The <strong>City</strong> <strong>of</strong> <strong>Waterville</strong> Maine<br />

Implementation and Financial <strong>Plan</strong> – Page 8-3<br />

<strong>Airport</strong> Solutions Group, LLC & The Louis Berger Group, Inc. December 2011