F2: Upgrade and Utilize Old Telford location for FBO operations<br />
Rather than build an entirely new FBO facility, this alternative requires investment to upgrade<br />
and rehabilitate the former FBO facility.<br />
Requires the relocation <strong>of</strong> the <strong>Airport</strong>‟s current Snow Removal Equipment (SRE) facility.<br />
Requires the former Telford apron to be rehabilitated (Apron rehab eligible for AIP funds, thus a<br />
private developer would not be responsible for apron rehabilitation costs).<br />
Current FBO hangar inadequate in size to accommodate large corporate type aircraft.<br />
With access improvements, this alternative <strong>of</strong>fers convenient ground access for FBO clients.<br />
F3: Develop FBO facilities <strong>of</strong>f <strong>of</strong> existing Runway 14 approach end<br />
Requires significant infrastructure development including a ground access road, aircraft apron<br />
and taxiway design and construction.<br />
Would “set the tone” for future airport development along the required associated taxiway.<br />
The <strong>City</strong> <strong>of</strong> <strong>Waterville</strong> Maine<br />
Alternatives Analysis – Page 4-11<br />
<strong>Airport</strong> Solutions Group, LLC & The Louis Berger Group, Inc. December 2011