- Page 1: EPHC National Wind Farm Development
- Page 5: Acknowledgements These Guidelines h
- Page 8 and 9: A.6.1 Site selection 28 A.6.2 Proje
- Page 12 and 13: The 20/20 target is challenging; ho
- Page 14 and 15: Table 1-1 Elements of a ‘wind far
- Page 16 and 17: 2 Principles for responsible wind f
- Page 18 and 19: 3 Wind Farm Specific Issues The spe
- Page 20 and 21: Specific noise limits are not provi
- Page 22 and 23: 3.5 Shadow flicker The issue Shadow
- Page 24 and 25: Guidance notes Heritage issues are
- Page 26 and 27: Table 4-1 Typical decision process
- Page 28 and 29: The studies and community consultat
- Page 31 and 32: A Community and Stakeholder Consult
- Page 33 and 34: • Responsive There is a comm
- Page 35 and 36: Figure A-1 IAP2 Public Participatio
- Page 37 and 38: Specific components which should be
- Page 39 and 40: Figure A-2 Example of Good Practice
- Page 41 and 42: Recording the occurrence and outcom
- Page 43 and 44: A.6.6 Decommissioning Planning & Co
- Page 45 and 46: Potential Stakeholders Consultation
- Page 47 and 48: B Noise B.1 Introduction This Appen
- Page 49 and 50: the converse. These Guidelines reco
- Page 51 and 52: The Standard should form the basis
- Page 53 and 54: Stage and methodology Construction
- Page 55 and 56: Other noise-sensitive uses such as
- Page 57 and 58: Table B-2 Existing state and territ
- Page 59 and 60: Establish background noise monitori
- Page 61 and 62:
As noted in Section 6.3.1 of AS4959
- Page 63 and 64:
predicted levels are significantly
- Page 65 and 66:
Prepare expert evidence (as require
- Page 67 and 68:
Undertake unattended monitoring to
- Page 69 and 70:
assessment of wind farm noise emiss
- Page 71 and 72:
B.4.5 Decommissioning Noise-related
- Page 73 and 74:
If a significant amount of time has
- Page 75 and 76:
B.7 Technical discussion of key con
- Page 77 and 78:
The HGC Engineering report 10 also
- Page 79 and 80:
C Landscape C.1 Introduction This A
- Page 81 and 82:
• Cumulative impacts “Cumulativ
- Page 83 and 84:
C.2 Overview of Methodologies Figur
- Page 85 and 86:
C.3 Task Methodologies C.3.1 Projec
- Page 87 and 88:
• State Relevant State herita
- Page 89 and 90:
The preliminary landscape character
- Page 91 and 92:
• Identifying and describing (in
- Page 93 and 94:
Advanced photomontages should also
- Page 95 and 96:
C.4.2 Visual Impact Assessment The
- Page 97 and 98:
C.4.2.4 Assessment of cumulative im
- Page 99 and 100:
the implementation of agreed change
- Page 101 and 102:
Figure C-2 IBRA mapping of Australi
- Page 103 and 104:
Table C-4 Mapping of landscape char
- Page 105 and 106:
C.7.2 Levels of significance What a
- Page 107 and 108:
Consider ‘Supporting Evidence’
- Page 109 and 110:
information available for other sit
- Page 111 and 112:
Figure C-4 Example of viewshed mapp
- Page 113 and 114:
Figure C-6 Example of photomontages
- Page 115 and 116:
communicate broad-scale ideas and p
- Page 117 and 118:
Table C-5 Mapping other wind farms
- Page 119 and 120:
C.7.9 Glossary & acronyms Australia
- Page 121:
Viewpoint The point from which a vi
- Page 124 and 125:
D.1.2 Underlying approach The under
- Page 126 and 127:
All of the above is generally appli
- Page 128 and 129:
the operational wind farm is aimed
- Page 130 and 131:
D.4 Task methodologies D.4.1 Site S
- Page 132 and 133:
area as it was not collected accord
- Page 134 and 135:
used throughout these Guidelines as
- Page 136 and 137:
wind farms. Such data from existing
- Page 138 and 139:
considered acceptable, undesirable,
- Page 140 and 141:
construction phase are identified d
- Page 142 and 143:
Searches for dead birds and bats ar
- Page 144 and 145:
D.5 Cumulative impacts D.5.1 Defini
- Page 146 and 147:
in the absence of any turbine colli
- Page 148 and 149:
that it was first observed. Where m
- Page 150 and 151:
e the case that assessment for bats
- Page 152 and 153:
Department of Primary Industries, W
- Page 154 and 155:
Percival, S.M. 2003, Birds and wind
- Page 157 and 158:
E Shadow Flicker E.1 Introduction T
- Page 159 and 160:
• The use of recreational facilit
- Page 161 and 162:
• The method is inherently linked
- Page 163 and 164:
Table E-1 Recommended exposure limi
- Page 165 and 166:
E.4.4 Construction Assessment of th
- Page 167 and 168:
E.7 Technical discussion of key con
- Page 169 and 170:
Figure E-4 Variation in shading wit
- Page 171 and 172:
common practice varies between one
- Page 173:
as the actual limit, rather than th
- Page 176 and 177:
likely to be obstructed. Radiocommu
- Page 178 and 179:
Licensed radiocommunications servic
- Page 180 and 181:
Figure F-1 EMI mitigation methodolo
- Page 182 and 183:
F.4 Task methodologies F.4.1 Projec
- Page 184 and 185:
Expected timeframe for evaluation r
- Page 186 and 187:
The near field zone can be calculat
- Page 188 and 189:
Develop mitigation strategy As a st
- Page 190 and 191:
aseline RF survey which involves th
- Page 193 and 194:
G Wind Farm Development Process G.1
- Page 195 and 196:
Project Sub-stages Activities to be
- Page 197 and 198:
Preliminary Technical Studies Issue
- Page 199 and 200:
Planning application (PA2) The plan
- Page 201 and 202:
Develop mitigation strategy Finalis
- Page 203 and 204:
Environmental Management Plans Issu
- Page 205 and 206:
Monitoring: confirmation (O3) Confi
- Page 207 and 208:
Decommissioning (D2) Once a decisio