Develop mitigation strategy<br />

Finalise mitigation strategy<br />

Project Sub-stages<br />

Activities to be Undertaken<br />

Planning Application<br />

PA1<br />

PA2<br />

Detailed Technical<br />

Studies<br />

Planning Application<br />

(in accordance with<br />

jurisdictional<br />

requirements)<br />

Purpose:<br />

To provide detailed site-specific data to enable optimisation of the<br />

project layout and assess the impacts of the project.<br />

Activity:<br />

Assess via desktop and site studies:<br />

• survey and mapping of the locations of residences and other<br />

infrastructure<br />

• planning (strategic policy context, development approval and<br />

permit requirements)<br />

• representative wind turbine generator selection<br />

• electrical connections and on-site infrastructure<br />

• noise<br />

• shadow flicker<br />

• landscape<br />

• ecology (flora and fauna)<br />

• cultural heritage<br />

• geotechnical conditions<br />

• water quality impacts<br />

• waste management<br />

• traffic and transportation management<br />

• aircraft safety<br />

• electromagnetic interference<br />

• socio-economic impacts.<br />

A best-practice planning application should also include:<br />

• the preferred wind farm layout<br />

• details of the proposed power connection options<br />

• details of the community and stakeholder management<br />

programme<br />

• Environmental Management Plan, including decommissioning<br />

• Emergency and Incident Management Plan<br />

• Fire Hazard Management Plan.<br />

Consultation:<br />

Significant stakeholder input will be required for the Landscape and<br />

EMI Technical Investigations.<br />

A Community Information Event or Events should be conducted at this<br />

stage to present the preliminary outcomes of the technical<br />

investigation process. Stakeholder feedback on the investigations and<br />

project design should be considered for incorporation and/or<br />

amendment in the project design as far as possible.<br />

A report of consultation conducted to date and its outcomes should<br />

be prepared for inclusion in the planning application documentation.<br />

Purpose:<br />

To present the proposed project and its impacts in a form suitable for<br />

planning authority and community assessment of the project.<br />

Activity:<br />

Prepare a planning application and supporting documentation<br />

incorporating the all technical reports and a summary of findings in<br />

plain English.<br />

Consultation:<br />

The planning application submission will be available for public<br />

exhibition. Stakeholders will have an opportunity to comment on the<br />

application to the relevant authorities, according to their statutory<br />

requirements.<br />