12.04.2015 Views

3720 - Board of Claims

3720 - Board of Claims

3720 - Board of Claims

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

Disruption Damages and Additional Work<br />

Intercounty claimed $364,480 in added costs for loss <strong>of</strong> productivity on the Project<br />

caused by PennDOT's active interference. It claims this active interference caused it to work in<br />

an out-<strong>of</strong>-sequence, non-linear manner vastly different and less efficient than outlined in the<br />

Construction Sequence originally prescribed by PennDOT in the bid documents and Contract.<br />

Intercounty also claims that it incurred an additional cost <strong>of</strong> $56,800 for the re-handling <strong>of</strong><br />

stockpiled fill material caused by the changes to the original Construction Sequence and an<br />

additional $278,965 for the undercutting work it did on the Project. It claims entitlement to this<br />

latter amount because it asserts that the quantity <strong>of</strong> undercutting was excessive and constituted an<br />

undisclosed site condition. It also claims it should be reimbursed for this undercutting at a<br />

higher rate than the $9 per cubic yard rate it quoted for Class 1 Excavation because it cost<br />

Intercounty considerably more to do undercutting than general excavation. Finally, it claims it<br />

incurred inefficiencies in doing this undercutting work since it was done out <strong>of</strong> sequence and in a<br />

non-linear fashion due to the utility pole relocation delay and resulting problems described at<br />

length in the liability section <strong>of</strong> this Opinion.<br />

The <strong>Board</strong> finds substantial merit to Intercounty's loss <strong>of</strong> productivity claim, no merit to<br />

its claim for re-handling stockpiled materials and mixed merit to its undercutting claim.<br />

Additionally the <strong>Board</strong> finds that some adjustment to Intercounty's damage calculations for these<br />

categories are needed to more accurately reflect the extra costs actually incurred on the Project<br />

due to PennDOT's active interference. We will address these claims together in this section.<br />

To begin with, the <strong>Board</strong> is fully satisfied that PennDOT's active interference with<br />

Intercounty's work on the SR 2001 Project, as enumerated above in this Opinion, caused<br />

substantial disruption and loss <strong>of</strong> productivity to Intercounty. PennDOT's representations<br />

100

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!