12.04.2015 Views

3720 - Board of Claims

3720 - Board of Claims

3720 - Board of Claims

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

section at a time contemplated by the Contract’s Construction Sequence. These actions by<br />

PennDOT were material changes to the Contract which actively interfered with Intercounty’s<br />

work and resulted in delay and lost productivity on the Project.<br />

Delayed Response to Design Problem<br />

Although PennDOT's active interference with Intercounty's work by way <strong>of</strong>: A) its<br />

misrepresentation that it would coordinate pole relocation at the start <strong>of</strong> the Project and its abject<br />

failure even to attempt to do so for the first six months <strong>of</strong> the Project and B) Mr. Sebastianelli’s<br />

unilateral dictates to Intercounty to abandon the Construction Sequence and work less productively<br />

due to the pole relocation problem rather than demobilize, were both material causes <strong>of</strong> the delay<br />

and disruption experienced by Intercounty on the Project, we find that PennDOT's initial design<br />

mistake (i.e. its failure to properly coordinate with the Utilities in the pre-Contract design phase<br />

and allow enough space in the right-<strong>of</strong>-way for the guy wires for certain <strong>of</strong> the utility poles in<br />

Section Two) and the nearly seven month delay in resolving this problem were even more<br />

significant causes <strong>of</strong> delay in relocating the utility poles and, in turn, the fundamental cause <strong>of</strong><br />

delay and disruption to Intercounty’s work on the Project. (N.T. 64-68). To begin with, we note<br />

that the guy wire problem itself was one <strong>of</strong> PennDOT’s own making. That is to say, even if it was<br />

the Utilities’ initial failure to identify guy wires for those certain poles at issue, it was PennDOT’s<br />

ultimate responsibility to authorize and approve the locations <strong>of</strong> the new poles and to properly<br />

situate them within its roadway design to allow the Project to be built as set forth in its plans and<br />

damages. (N.T. 58-69). 408 Specifications § 104.01; United States v. Spearin, 248 U.S. 132, 137,<br />

39 S. Ct. 59, 61 (1918); Canuso v. City <strong>of</strong> Philadelphia, 192 A. 133, 136 (Pa. 1937); A.G. Cullen<br />

Construction, 898 A.2d at 1160; Department <strong>of</strong> Transportation v. W.P. Dickerson & Son, Inc., 400<br />

A.2d 930, 932 (Pa. Cmwlth. 1979); Allentown Supply Corp. v. Stryer, 195 A.2d 274, 279 (Pa.<br />

84

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!