12.04.2015 Views

3720 - Board of Claims

3720 - Board of Claims

3720 - Board of Claims

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

egarding what PennDOT could do to make room for the guy wires. Possible solutions discussed<br />

included redesign <strong>of</strong> the area or acquisition <strong>of</strong> additional rights-<strong>of</strong>-way from the adjacent<br />

landowner. However, PennDOT quickly determined it would not pay for additional rights-<strong>of</strong>way.<br />

(N.T. 93-94, 119-120, 289, 598; Exs. P-3, P-4, P-14, P-59).<br />

76. PennDOT’s original design did not allow sufficient room for guy wires in the<br />

right-<strong>of</strong>-way at several new pole locations along the Project, although PennDOT itself had<br />

authorized and approved these new pole locations by permit. (Exs. P-3, P-4, P-59; F.O.F. 75;<br />

<strong>Board</strong> Finding).<br />

77. Prior to PennDOT’s soliciting bids for this Project, the Utility Relocation Unit<br />

failed to determine what, if any, special right-<strong>of</strong>–way requirements there might be for the new<br />

pole locations, and PennDOT’s designers failed to allow sufficient space in the right-<strong>of</strong>-way for<br />

the guy wires that supported some <strong>of</strong> the new, relocated utility poles. (N.T. 61-64, 69, 1121-<br />

1123; F.O.F. 67-76; <strong>Board</strong> Finding).<br />

78. Although guy wires may have affected and prevented placement <strong>of</strong> only a few<br />

poles, the inability to place all <strong>of</strong> the new poles in the right-<strong>of</strong>-way prevented transfer or<br />

restringing <strong>of</strong> the utility wires in the affected section. This, in turn, precluded removal <strong>of</strong> old<br />

poles (and thereby impeded building the new roadway) until a final resolution <strong>of</strong> all guy wire<br />

pole placement problems. (N. T. 81, 93, 230-231; Exs. P-25, P-59; F.O.F. 68-77, 134-135,<br />

170-196; <strong>Board</strong> Finding).<br />

79. PennDOT provided design specifications for the Project by prescribing the<br />

character, dimensions, location and other design details for reconstruction and paving <strong>of</strong> the<br />

Project roadway in the Project’s plans, drawings, specifications, permits and Contract. (F.O.F.<br />

4-5, 24-78; <strong>Board</strong> Finding).<br />

80. By prescribing the location <strong>of</strong> new utility poles through its permitting process for<br />

this Project and then prescribing the character, dimensions, location and other design<br />

specifications for reconstruction and paving <strong>of</strong> the Project roadway, but failing to provide<br />

sufficient room within its rights-<strong>of</strong>-way for guy wires (as needed) on these new poles in its plans<br />

and design; PennDOT failed to provide Project plans adequate to construct the Project. (F.O.F.<br />

24-79, 134-135, 170-196; <strong>Board</strong> Finding).<br />

81. Because PennDOT failed to provide plans adequate to construct the Project,<br />

PennDOT failed to act in a matter necessary for prosecution <strong>of</strong> the work on the Project and<br />

actively and materially interfered with Intercounty’s work on the Project. (F.O.F. 24-80, 134-<br />

135, 170-196; <strong>Board</strong> Finding).<br />

82. The documents and evidence in this case, including Mr. Pilosi’s own testimony<br />

describing his job and his actions with regard to the Project, establish that PennDOT attempted to<br />

coordinate the utility pole and wire relocations needed for the Project in the pre-Contract period<br />

pursuant to its own internal policies and procedures. (F.O.F. 24-80; <strong>Board</strong> Finding).<br />

11

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!