during the pre-Contract period, and thereby failed to take actions reasonably within its capability<br />
to provide Intercounty with access to work on the Project. (F.O.F. 24-87; <strong>Board</strong> Finding).<br />
89. Because PennDOT failed to adequately coordinate the utility pole and wire<br />
relocation for the Project during the pre-Contract period, and thereby failed to take actions<br />
reasonably within its capability to provide Intercounty with reasonably unobstructed access to<br />
work on the Project, PennDOT actively and materially interfered with Intercounty’s work.<br />
(F.O.F. 24-88; <strong>Board</strong> Finding).<br />
90. Because PennDOT provided Intercounty with final plans and drawings that did<br />
not allow sufficient space for pole relocations with guy wires, PennDOT failed to adequately<br />
coordinate the utility pole relocations in the pre-Contract design phase. (F.O.F. 24-46, 67-82;<br />
<strong>Board</strong> Finding).<br />
POST-CONTRACT ACTIVITY<br />
91. In April 2001, the Contract drafted by PennDOT was circulated to various<br />
qualified contractors, including Intercounty, for public bidding. Bids were received and opened<br />
on April 19, 2001. (Exs. P-6, P-8, P-87).<br />
92. Intercounty was the lowest responsible bidder and was awarded the Contract on<br />
May 18, 2001. (Ex. P-11).<br />
93. On May 23, 2001, PennDOT sent Intercounty a notice that it had been awarded<br />
the Contract and requested Intercounty’s representatives attend a pre-construction conference on<br />
June 4, 2001. Mr. Pilosi sent a copy <strong>of</strong> this letter to the Utilities. (Ex. P-7).<br />
94. On June 4, 2001, PennDOT held a pre-construction conference with<br />
representatives <strong>of</strong> Intercounty and the Utilities. The minutes <strong>of</strong> that meeting state that, “Mr.<br />
Pilosi reviewed the public utility involvement in the project.” (N.T. 589; Exs. P-7, P-9, P-11, P-<br />
27).<br />
95. There is no further evidence in the record regarding the substance <strong>of</strong> any<br />
conversations at the June 4, 2001 meeting respecting utility relocations. (N.T. 589; Exs. P-7, P-<br />
9, P-11, P-27; <strong>Board</strong> Finding).<br />
10).<br />
96. On June 5, 2001, PennDOT completed execution <strong>of</strong> the Contract. (Exs. P-8, P-<br />
97. On June 11, 2001, PennDOT held a pre-job meeting at the Project site with<br />
representatives from Intercounty, PennDOT, the Utilities and the Pike County Conservation<br />
District. Mr. Pilosi had notified the Utilities to attend and he chaired the meeting. (N.T. 87-88,<br />
138-141, 149; Ex. P-7).<br />