12.04.2015 Views

3720 - Board of Claims

3720 - Board of Claims

3720 - Board of Claims

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

214. PennDOT clearly misled Intercounty into believing PennDOT was making efforts<br />

to expedite pole and wire relocations (when in fact, it was not) by reason <strong>of</strong>: Mr. Pilosi’s<br />

representations made at the June 11, 2001 meeting that all further coordination with the Utilities<br />

would be handled by Mr. Pilosi and/or PennDOT; Mr. Sebastianelli’s actions thereafter<br />

confirming same throughout the remainder <strong>of</strong> the Project; the failure <strong>of</strong> anyone from PennDOT<br />

to advise Intercounty that it should be dealing directly with the Utilities regarding pole relocation<br />

issues during the Project; and Mr. Pilosi’s complete failure to do anything to facilitate utility pole<br />

and wire relocation during the first six months <strong>of</strong> the Project. The <strong>Board</strong> finds the foregoing<br />

combination <strong>of</strong> representations and continued inaction by PennDOT particularly troublesome<br />

after the Utilities left the Project in mid-October 2001 after completing only Section Three and it<br />

was obvious that utility pole relocation was severely delayed at that point. (N.T. 140-141, 231,<br />

619; F.O.F. 109-114, 117-118, 134-135, 152-157, 210-213; <strong>Board</strong> Finding).<br />

215. By misleading Intercounty into believing PennDOT was making efforts to<br />

expedite utility pole and wire relocation when it was not, PennDOT actively and materially<br />

interfered with Intercounty’s work on the Project. (N.T. 140-141, 231, 619; F.O.F. 109-114,<br />

117-118, 134-135, 152-157, 210-214; <strong>Board</strong> Finding).<br />

216. PennDOT actively interfered with Intercounty’s work by making affirmative<br />

representations which misled Intercounty into thinking that PennDOT was communicating its<br />

concerns with pole and wire relocations to the Utilities and was taking action to expedite the<br />

Utilities’ performance, when, in fact, PennDOT was not doing so for the first six months <strong>of</strong> the<br />

Project. (F.O.F. 109-114, 117-118, 134-135, 152-157, 210-215; <strong>Board</strong> Finding).<br />

217. PennDOT’s refusal to consider a work suspension after the Utilities left the<br />

Project in mid-October 2001 (with only a small portion <strong>of</strong> the pole relocations accomplished)<br />

and its direction to Intercounty to work in an unplanned, out <strong>of</strong> sequence and piecemeal way<br />

under the ad hoc weekly work schedules created by PennDOT (instead <strong>of</strong> pursuant to the<br />

Construction Sequence) materially altered the Contract’s prescribed work sequences and<br />

hindered Intercounty’s work for the remainder <strong>of</strong> the Project. (Exs. P-8, P-59; F.O.F. 133-145,<br />

173-202; <strong>Board</strong> Finding).<br />

218. PennDOT actively interfered with Intercounty’s work on the Project by materially<br />

altering the Contract’s prescribed work sequences from mid-October 2001 onward. (F.O.F. <br />

133-145, 173-202; <strong>Board</strong> Finding).<br />

219. PennDOT actively interfered with Intercounty’s performance by its acts <strong>of</strong><br />

abandoning the Construction Sequence, refusing to suspend work and insisting that Intercounty<br />

work in an unplanned, piecemeal fashion instead <strong>of</strong> the planned, linear sequence <strong>of</strong> construction<br />

steps. (F.O.F. 133-145, 173-202; <strong>Board</strong> Finding).<br />

220. PennDOT actively interfered with Intercounty’s work on the Project and failed to<br />

act in a manner necessary to the prosecution <strong>of</strong> the work by its initial failure to plan enough room<br />

for guy wires as needed for several new poles on the Project and then by PennDOT’s excessively<br />

long delay in resolving the right-<strong>of</strong>-way/guy wire design problem (from August 2001 to March<br />

2002). (F.O.F. 24-81, 134-135, 145, 165, 168, 170-196; <strong>Board</strong> Finding).<br />

29

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!