12.04.2015 Views

3720 - Board of Claims

3720 - Board of Claims

3720 - Board of Claims

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

the pre-Contract period. Specifically, PennDOT’s failure to provide the Utilities with the<br />

Construction Sequence and the final plans and drawings for the Project until immediately before<br />

the start <strong>of</strong> work; PennDOT's failure to indicate poles to be moved and the position <strong>of</strong> the new<br />

poles on its plans and drawings; and, most importantly, its failure to provide adequate space for<br />

guy wires on certain relocated poles in its roadway design, together, constituted a failure to<br />

properly coordinate utility pole relocation for the Project in the pre-Contract period and failure to<br />

provide Intercounty with plans and drawings adequate to build the Project. These acts and<br />

omissions actively interfered with Intercounty’s work and exhibit a failure on PennDOT's part to<br />

act in an essential matter necessary to the prosecution <strong>of</strong> the Project. 11<br />

Post-Contract Activity<br />

In April 2001, PennDOT issued its invitation to bid on the Project. Bids were received<br />

and opened on April 19, 2001. On June 5, 2001 PennDOT became the last party to execute the<br />

Contract with Intercounty to perform the work on the Project. On June 11, 2001, PennDOT held<br />

a pre-job meeting near the site attended by representatives from GPU, G.T.E, Blue Ridge<br />

(collectively, the "Utilities") PennDOT, Intercounty, and the Pike County Conservation District.<br />

Mr. Pilosi had arranged for the Utilities to be present.<br />

During the June 11 pre-job meeting, the Utilities indicated that PennDOT had never<br />

given them the Contract’s Construction Sequence. As a result, the Utilities had not had any<br />

opportunity to see or consider the Construction Sequence prior to June 11, 2001 for planning<br />

their work schedules for the Project. In fact, the Utilities had come to this pre-job meeting<br />

unaware <strong>of</strong> the necessity <strong>of</strong> starting in Section One and performing their work in discrete<br />

sections and phases and at different periods <strong>of</strong> time as the Project progressed, and stated they<br />

11 As will become evident later, the Utilities, albeit late, did eventually relocate their poles in Section Three by late<br />

October 2001, but then left the Project and did not return until late March 2002, only after resolution <strong>of</strong> the guy wire<br />

design problem and relocation <strong>of</strong> the roadway in March 2002.<br />

72

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!