utility, GPU Energy ("GPU") informed PennDOT it would need eighty-one days to relocate its<br />

poles and wires along the roadway. A third utility, Blue Ridge Communications (the TV cable<br />

company), had its cables strung on the G.T.E. and GPU poles along the roadway. Blue Ridge<br />

told PennDOT it required sixty days to reattach its cable lines on the relocated G.T.E. and GPU<br />

poles.<br />

As a result <strong>of</strong> this initial communication with the Utilities early in the Project's planning<br />

and design phase, Joseph Pilosi, PennDOT’s District 4-0 Utilities Relocation Administrator in<br />

charge <strong>of</strong> utilities coordination on the Project, caused PennDOT to issue permits to the Utilities<br />

to relocate their poles. These permits specifically named each new pole and indicated future<br />

location. 7<br />

Mr. Pilosi also drafted a special provision for the Contract, entitled, “Utilities” which<br />

described to the bidding contractors the time period each utility would occupy the Project site to<br />

relocate the utility poles. (Exs. P-2B, P-3, P-4). As noted above, this section indicated the pole<br />

relocation was to be performed in a "coordinated" manner, commencing after the successful<br />

bidding contractor did initial survey and elevation markings; proceeding thereafter with the<br />

roadway contractor’s early stages <strong>of</strong> work; and taking approximately 81 days for the utility<br />

company requiring the longest time frame to complete its pole relocation (GPU).<br />

However, from these early communications between PennDOT and the Utilities in late<br />

December 1999/early January 2000, until PennDOT notified the Utilities by letter <strong>of</strong> May 23,<br />

2001 that Intercounty had been awarded the Contract, the evidentiary record is devoid <strong>of</strong> any<br />

interim communication between PennDOT and the Utilities respecting this Project. It is this<br />

period prior to the award <strong>of</strong> the Contract to which Intercounty first points in asserting<br />

PennDOT's initial failure to properly plan, schedule and coordinate the utility pole relocation for<br />

7 See Exs. P-2B, P-3 and P-4. As was the case here, PennDOT provides utilities with the ability to use PennDOT's<br />

right-<strong>of</strong>-way to place utility poles and has the accompanying right to require the utilities to relocate these poles as it<br />

directs. N.T. 57-58, 86; 36 P.S. § 670-411, 67 Pa. Code § 459.1 et seq.<br />