12.04.2015 Views

3720 - Board of Claims

3720 - Board of Claims

3720 - Board of Claims

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

performance, the Contract’s exculpatory provisions, relied upon by PennDOT to relieve it from<br />

liability for delay and disruption damages on the Project, are not enforceable. Coatesville<br />

Contractors, 506 A.2d at 865-866; Gasparini, 187 A.2d at 163; General Asphalt Paving, 408 A.2d<br />

at 1141; Sheehan v. Pittsburgh, 62 A. at 624.<br />

46. Delay caused by an owner’s failure to obtain the rights-<strong>of</strong>-way necessary to build a<br />

roadway project is not in the class <strong>of</strong> difficulties generally contemplated by the parties, since the<br />

roadway construction agreement is based on the assumption by both parties that all the necessary<br />

rights-<strong>of</strong>-way have been secured and the work can proceed without interruption. Sheehan v.<br />

Pittsburgh, 62 A. 642 (Pa. 1905).<br />

47. In addition to its initial failure to plan enough room for guy wires as needed on the<br />

new poles on the Project, PennDOT’s long delay in resolving the pole relocation right-<strong>of</strong>-way<br />

problem (from August 2001 to March 2002) was another instance <strong>of</strong> PennDOT’s failure to act in<br />

an essential matter necessary to the prosecution <strong>of</strong> the work on this Project and itself constituted a<br />

material breach <strong>of</strong> the Contract and active interference with Intercounty’s work on the Project.<br />

Coatesville Contractors, 506 A.2d at 865-867; Pittsburgh Building Co., 920 A.2d at 987; A.G.<br />

Cullen, 898 A.2d at 1160; C.J. Langenfelder & Son, Inc., 404 A.2d at 750-751.<br />

48. PennDOT’s long delay in resolving the pole relocation right-<strong>of</strong>-way problem (from<br />

August 2001 to March 2002) constitutes additional grounds for refusal to enforce the exculpatory<br />

clauses relied upon by PennDOT to relieve it from liability for delay and disruption damages on<br />

the Project. Sheehan v. Pittsburgh, 62 A. at 642; Pittsburgh Building, 920 A.2d at 991; General<br />

Asphalt Paving, 405 A.2d at 1141; Gasparini, 187 A.2d at 162-163; S.J. Groves & Sons, Co., 343<br />

A.2d at 74-76; James Corp., 938 A.2d at 484.<br />

49. Because we have found that PennDOT actively interfered with Intercounty’s work<br />

on the Project and materially breached the Contract by way <strong>of</strong> the following acts/omissions on the<br />

Project:<br />

A. PennDOT’s failure to provide plans and drawings adequate to construct<br />

the Project;<br />

B. PennDOT’s failure to act in an essential matter necessary to the prosecution <strong>of</strong> work<br />

on the Project by its failure to adequately coordinate utility pole and wire relocation on the<br />

Project in the pre-Contract design phase <strong>of</strong> same;<br />

C. PennDOT’s affirmative misrepresentations to Intercounty which misled Intercounty<br />

into thinking that PennDOT was communicating its concerns with pole and wire<br />

relocations to the utility companies and was taking action to expedite the utility companies’<br />

performance, when in fact, PennDOT was not doing so for the first six months <strong>of</strong> the<br />

Project;<br />

D. PennDOT’s denial <strong>of</strong> a work suspension after the utility companies left the Project<br />

in mid-October 2001 with only a small portion <strong>of</strong> the pole relocation accomplished and its<br />

direction to Intercounty to work in an unplanned, piecemeal way under the ad hoc weekly<br />

55

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!