12.04.2015 Views

3720 - Board of Claims

3720 - Board of Claims

3720 - Board of Claims

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

21. By prescribing the character, dimensions, location and other design specifications<br />

for reconstruction and paving <strong>of</strong> the Project roadway, PennDOT provided design specifications for<br />

these tasks and warranted to Intercounty that these plans and specifications would be adequate to<br />

construct the Project. United States v. Spearin, 248 U.S. at 137, 39 S. Ct. at 61; Canuso v. City <strong>of</strong><br />

Philadelphia, 192 A. at 136; A.G. Cullen Construction, 898 A.2d at 1160; W.P. Dickerson & Son,<br />

400 A.2d at 932; Allentown Supply Corp. v. Stryer, 195 A.2d at 279.<br />

22. Delays and damages incurred in construction occasioned by the necessity <strong>of</strong> altering<br />

plans because <strong>of</strong> an owner’s failure to originally provide adequate design are properly charged to<br />

the owner. C.J. Langenfelder & Son, Inc. v. Department <strong>of</strong> Transportation, 404 A.2d 745 (Pa.<br />

Cmwlth. 1979).<br />

23. PennDOT also had the responsibility for securing all necessary rights-<strong>of</strong>-way for<br />

the Project in advance <strong>of</strong> construction. 408 Specifications, § 107.18; Sheehan v. City <strong>of</strong><br />

Pittsburgh, 62 A. 642 (Pa. 1905).<br />

24. Intercounty established by substantial evidence that PennDOT did not properly plan<br />

for sufficient rights-<strong>of</strong>-way to accommodate the guy wires at several new pole locations. DGS v.<br />

Pittsburgh Building Co., 902 A.2d at 989.<br />

25. Because PennDOT failed to provide Project plans and design adequate to construct<br />

the Project (by prescribing the location <strong>of</strong> the new utility poles through its permitting process for<br />

this Project and then prescribing the character, dimensions, location and other design specifications<br />

for reconstruction and paving <strong>of</strong> the Project roadway, but failing to provide sufficient room within<br />

its rights-<strong>of</strong>-way for guy wires (as needed) on these new poles in its plans and design), PennDOT<br />

materially breached the Contract and actively interfered with Intercounty’s work on the Project.<br />

United States v. Spearin, 248 U.S. at 137, 39 S. Ct. at 61; Canuso v. City <strong>of</strong> Philadelphia, 192 A. at<br />

136; A.G. Cullen Construction, 898 A.2d at 1160; W.P. Dickerson & Son, 400 A.2d at 932;<br />

Allentown Supply Corp. v. Stryer, 195 A.2d at 279.<br />

26. Because PennDOT failed to adequately coordinate the utility pole and wire<br />

relocation for the Project during the pre-Contract design phase, and thereby failed to act in a matter<br />

necessary for prosecution <strong>of</strong> work on the Project (by, inter alia: prescribing the location <strong>of</strong> the new<br />

utility poles through its permitting process for this Project and then prescribing the character,<br />

dimensions, location and other design specifications for reconstruction and paving <strong>of</strong> the Project<br />

roadway, but failing to provide sufficient room within its rights-<strong>of</strong>-way for guy wires (as needed)<br />

on these new poles in its plans and design; failing to provide the utility companies affected by the<br />

Project with the Construction Sequence and the final plans for the Project sufficiently in advance<br />

<strong>of</strong> the start <strong>of</strong> actual work on the Project site so these utility companies could effectively plan<br />

ahead for the timing and sequencing <strong>of</strong> the pole relocation work prescribed by the Contract; and<br />

failing to indicate the old utility poles to be removed and/or the location <strong>of</strong> the new utility poles to<br />

be installed on these final plans and drawings), PennDOT materially breached the Contract and<br />

actively interfered with Intercounty’s work. See e.g., Coatesville Contractors, 506 A.2d at 865-<br />

867; General Asphalt Paving, 405 A.2d at 1140-1141; Gasparini, 187 A.2d 161-162; S.J Groves &<br />

Sons, Co., 343 A.2d at 76; Sheehan v. Pittsburgh, 62 A. at 642; Pittsburgh Building Co., 920 A.2d<br />

at 987.<br />

49

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!