12.04.2015 Views

3720 - Board of Claims

3720 - Board of Claims

3720 - Board of Claims

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

work schedules created by PennDOT instead <strong>of</strong> pursuant to the Construction Sequence<br />

mandated by the Contract;<br />

E. PennDOT’s failure to act in an essential matter necessary to prosecution <strong>of</strong> work on<br />

the Project by reason <strong>of</strong> its long delay in resolving the pole relocation right-<strong>of</strong>-way problem<br />

(from August 2001 to March 2002);<br />

and because we have also found that these same acts/omissions caused the Project to be delayed<br />

for the full 223 days claimed, and disrupted Intercounty’s work throughout the Project, we find<br />

PennDOT liable to Intercounty for delay and disruption damages set forth below. See Conclusion<br />

<strong>of</strong> Law 25-27, 38-48.<br />

50. Although pro<strong>of</strong> <strong>of</strong> damages cannot be mere guess or speculation, the exact amount<br />

<strong>of</strong> damages need not be calculated with mathematical precision. Where an amount <strong>of</strong> damages<br />

may be fairly estimated from the evidence, a recovery will be sustained even though such amount<br />

cannot be determined with entire accuracy. See e.g., Spang & Co. v. U.S. Steel Corp., 545 A.2d<br />

861, 866-67 (Pa. 1988).<br />

51. Evidence <strong>of</strong> damages may consist <strong>of</strong> probabilities and inferences as long as the<br />

amount is shown with reasonable certainty. A.G. Cullen, 898 A.2d at 1161; C. Ernst, Inc. v.<br />

Koppers Co., Inc., 626 F.2d 324 (3 rd Cir. 1980).<br />

52. Sections 110.03(d)(4) and (7) <strong>of</strong> the 408 Specifications prescribe markups for Extra<br />

Work that are frequently and fairly used to determine appropriate markup for additional cost<br />

claims in PennDOT contract actions. These markups are 40% for labor; 25% for materials; 5% for<br />

equipment; and an additional 8% for subcontract work. 408 Specifications § 110.03(d)(4) and (7).<br />

53. The markups in Sec. 110.03 (d)(4) and (7) to cost are intended to compensate the<br />

contractor, inter alia, for administration, general and project superintendence, bond costs, overhead<br />

and pr<strong>of</strong>it. Id.<br />

54. Because we have found that PennDOT caused the 223 days <strong>of</strong> delay on the Project<br />

and that Intercounty incurred additional costs on the Project in that extended period (the 223 days<br />

<strong>of</strong> delay) in the amount <strong>of</strong> $11,530.27 for Extended Field Conditions, PennDOT is liable to<br />

Intercounty for these costs, plus appropriate markup pursuant to Section 110.03(d)(4) and (7) in<br />

the total amount <strong>of</strong> $12,470.02 for Extended Field Conditions. Id.<br />

55. Because we have found that Intercounty also incurred extra costs for the<br />

Maintenance and Protection <strong>of</strong> Traffic in the extended period <strong>of</strong> the Project (the 223 days <strong>of</strong> delay)<br />

caused by PennDOT in the amount <strong>of</strong> $10,578.16, PennDOT is liable to Intercounty for these costs<br />

plus appropriate markup pursuant to Section 110.03(d)(4) and (7) in the total amount <strong>of</strong><br />

$14,225.79 for this damage item. Id.<br />

56. Because we have already applied the markups prescribed by Section 110.03(d)(4)<br />

and (7) to Intercounty’s other costs and because these markups are intended to compensate<br />

56

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!