12.04.2015 Views

3720 - Board of Claims

3720 - Board of Claims

3720 - Board of Claims

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

38. In late 1999, two years before construction work on the Project began, Mr. Pilosi<br />

sent each <strong>of</strong> the Utilities a Utility Relocation Questionnaire and Permit Application<br />

(“Questionnaire”) along with PennDOT’s preliminary design plans and drawings for the Project<br />

on which he had identified the poles that were in conflict with the new road plan. (N.T. 41-42,<br />

45, 58-59; Exs. P-3, P-4).<br />

39. After the Utilities reviewed the preliminary plans and information that Mr. Pilosi<br />

had sent them, each utility company identified what new facilities it needed to install in the<br />

PennDOT right-<strong>of</strong>-way and the time estimate each company would need for doing its work.<br />

(N.T. 44-45, 59; Exs. P-3, P-4).<br />

40. Each utility company then sent its response to the Questionnaire to Mr. Pilosi, and<br />

GTE and GPU applied for permits that specified each new pole location. (N.T. 42-55; Exs. P-3,<br />

P-4).<br />

41. Based upon the plans and information provided by Mr. Pilosi, GTE and GPU<br />

identified in their permit applications each new pole to be installed by pole number. (N.T. 41-42,<br />

44, 58-60; Exs. P-3, P-4).<br />

42. In November 1999, G.T.E.’s application to PennDOT for a relocation permit<br />

stated that G.T.E. would need 60 days to relocate 15 <strong>of</strong> its poles at the specified locations along<br />

the roadway and relocate its wires. (N.T. 45-54, 87; Ex. P-3).<br />

43. In December 1999, PennDOT’s Bureau <strong>of</strong> Design’s Right-<strong>of</strong> Way and Utilities<br />

Section approved G.T.E.’s application and issued G.T.E. a permit to relocate its 15 identified<br />

poles at the designated locations and to complete its work within 60 days. (N.T. 45, 57; Ex. P-3).<br />

44. In December 1999, GPU’s application to PennDOT for a relocation permit stated<br />

GPU would need 81 days to relocate 41 <strong>of</strong> its poles at the specified locations along the roadway<br />

and relocate its wires. (N.T. 51, 70-71, 87; Ex. P-4).<br />

45. In January 2000, PennDOT’s Bureau <strong>of</strong> Design’s Right-<strong>of</strong> Way and Utilities<br />

Section approved GPU’s application and issued GPU a permit to relocate its 41 identified poles<br />

at the designated locations and to complete its work within 81 days. (N.T. 57, 69-71; Ex. P-4).<br />

46. Blue Ridge Communications had its cables strung on the G.T.E. and GPU poles<br />

along the roadway, and it informed PennDOT it needed 60 days to relocate its cables in all<br />

sections. (N.T. 50, 55; Ex. P-2B).<br />

47. Also as part <strong>of</strong> his duties as District 4-0 Utilities Relocation Administrator,<br />

Mr. Pilosi drafted a special provision entitled “Utilities” which was included in the bid and<br />

Contract documents. This provision described to the bidding contractors the time period each<br />

utility would occupy the Project site while it relocated its poles and/or wires. (N.T. 34, 47; Exs.<br />

P-2B, P-8, P-34).<br />

7

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!