3720 - Board of Claims
3720 - Board of Claims
3720 - Board of Claims
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
38. In late 1999, two years before construction work on the Project began, Mr. Pilosi<br />
sent each <strong>of</strong> the Utilities a Utility Relocation Questionnaire and Permit Application<br />
(“Questionnaire”) along with PennDOT’s preliminary design plans and drawings for the Project<br />
on which he had identified the poles that were in conflict with the new road plan. (N.T. 41-42,<br />
45, 58-59; Exs. P-3, P-4).<br />
39. After the Utilities reviewed the preliminary plans and information that Mr. Pilosi<br />
had sent them, each utility company identified what new facilities it needed to install in the<br />
PennDOT right-<strong>of</strong>-way and the time estimate each company would need for doing its work.<br />
(N.T. 44-45, 59; Exs. P-3, P-4).<br />
40. Each utility company then sent its response to the Questionnaire to Mr. Pilosi, and<br />
GTE and GPU applied for permits that specified each new pole location. (N.T. 42-55; Exs. P-3,<br />
P-4).<br />
41. Based upon the plans and information provided by Mr. Pilosi, GTE and GPU<br />
identified in their permit applications each new pole to be installed by pole number. (N.T. 41-42,<br />
44, 58-60; Exs. P-3, P-4).<br />
42. In November 1999, G.T.E.’s application to PennDOT for a relocation permit<br />
stated that G.T.E. would need 60 days to relocate 15 <strong>of</strong> its poles at the specified locations along<br />
the roadway and relocate its wires. (N.T. 45-54, 87; Ex. P-3).<br />
43. In December 1999, PennDOT’s Bureau <strong>of</strong> Design’s Right-<strong>of</strong> Way and Utilities<br />
Section approved G.T.E.’s application and issued G.T.E. a permit to relocate its 15 identified<br />
poles at the designated locations and to complete its work within 60 days. (N.T. 45, 57; Ex. P-3).<br />
44. In December 1999, GPU’s application to PennDOT for a relocation permit stated<br />
GPU would need 81 days to relocate 41 <strong>of</strong> its poles at the specified locations along the roadway<br />
and relocate its wires. (N.T. 51, 70-71, 87; Ex. P-4).<br />
45. In January 2000, PennDOT’s Bureau <strong>of</strong> Design’s Right-<strong>of</strong> Way and Utilities<br />
Section approved GPU’s application and issued GPU a permit to relocate its 41 identified poles<br />
at the designated locations and to complete its work within 81 days. (N.T. 57, 69-71; Ex. P-4).<br />
46. Blue Ridge Communications had its cables strung on the G.T.E. and GPU poles<br />
along the roadway, and it informed PennDOT it needed 60 days to relocate its cables in all<br />
sections. (N.T. 50, 55; Ex. P-2B).<br />
47. Also as part <strong>of</strong> his duties as District 4-0 Utilities Relocation Administrator,<br />
Mr. Pilosi drafted a special provision entitled “Utilities” which was included in the bid and<br />
Contract documents. This provision described to the bidding contractors the time period each<br />
utility would occupy the Project site while it relocated its poles and/or wires. (N.T. 34, 47; Exs.<br />
P-2B, P-8, P-34).<br />
7