30. Section 105.06(a) <strong>of</strong> the 408 Specifications provides, in part:<br />

Upon execution <strong>of</strong> the contract, inform all public service companies, individuals,<br />

and others owning or controlling any facilities or structures within the limits <strong>of</strong><br />

the project which may have to be relocated, adjusted, or reconstructed, <strong>of</strong> the plan<br />

<strong>of</strong> construction operations. Give due notice to the responsible party in sufficient<br />

time for that party to organize and perform such work in conjunction with or in<br />

advance <strong>of</strong> construction operations.<br />

Make all necessary arrangements with the owners <strong>of</strong> facilities and structures on,<br />

under, or over the project site and all waste and borrow areas not on the project<br />

site for any placement, replacement, relocation, adjustment, or reconstruction <strong>of</strong><br />

such facilities and structures that might be needed to perform work on this<br />

contract. Cooperate with the owners <strong>of</strong> facilities and structures in order to assist<br />

the owners in their placement, replacement, relocation, adjustment, or<br />

reconstruction operations. Arrange and perform the work in accordance with the<br />

recognized and accepted engineering and construction practices. As provided in<br />

Section 105.06(b), the Engineer may assist in resolving any construction problems<br />

that arise. However, the Department does not assume responsibility for the work<br />

as a consequence <strong>of</strong> such cooperation.<br />

Ex. P-60 at p. 102-2.<br />

31. Section 102.05 <strong>of</strong> the 408 Specifications provides, in part:<br />

Time estimates for the placement, replacement, relocation, adjustment and<br />

reconstruction <strong>of</strong> public and private facilities and structures on, under, or over the<br />

project and waste and borrow areas not on the project before and during the<br />

performance <strong>of</strong> the work have been provided only for informational purposes.<br />

The Department does not warrant the accuracy <strong>of</strong> the time estimates. Bidders<br />

should verify this information by contacting the owners <strong>of</strong> the facilities and<br />

structures. These time estimates are not to be considered part <strong>of</strong> the bid proposal.<br />

Ex. P-60 at p. 102-5.<br />

32. Paragraph 6 <strong>of</strong> the Contract provides:<br />

The contractor further covenants that he has not relied upon any information<br />

provided by the Department, including information contained in the Special<br />

Provisions, concerning the time within which publicly or privately-owned<br />

facilities below, at or above the ground are expected to be installed, removed,<br />

repaired, replaced, and/or relocated; that he has not relied upon any information<br />

provided by the Department concerning the location or existence <strong>of</strong> all such<br />

facilities that might be below, at or above ground; that he has contacted or will<br />

contact all owners <strong>of</strong> such facilities to verify the location and position <strong>of</strong> all such<br />

facilities and the time within which work on such facilities will be performed; and<br />